Key Highlights
- Catalyst Metals (ASX:CYL) produced 22,231 ounces and sold 27,229 ounces of gold in the September quarter.
- FY27 guidance is 90,000 to 105,000 ounces of gold at an All-In Sustaining Cost of AUD 3,600 to AUD 4,100 per ounce.
- The company moved expected production from Trident underground and Old Highway into FY28.
- Cash and bullion rose AUD 40 million to AUD 371 million, and the upsized revolving Credit Facility remained undrawn.
Catalyst Metals (ASX:CYL) revised its production schedule for the Plutonic Gold Belt in Western Australia in its September 2026 quarterly report. The company moved output from two projects into FY28 after reporting permitting delays at Old Highway and a slower start to underground development at Trident. Its October filing also reported quarterly production, updated spending guidance and an enlarged revolving credit facility.
Quarterly production across the Plutonic belt
Catalyst sold 27,229 ounces during the September quarter at an all-in sustaining cost of AUD 3,512 per ounce. It produced 22,231 ounces and said lower staffing levels had affected output. Catalyst expects Plutonic Main, Plutonic East and Keillor to Supply ore during FY27, along with the remaining stockpile from the Trident open pit.
Plutonic Main remained the principal source of plant feed. Catalyst aimed to increase ore from that mine as vacancies and charter flight arrangements returned to normal. The company declared commercial production at Keillor while work continued on power, communications and internal reporting. Approximately 63,000 tonnes of Trident open pit stockpiles were processed during the September quarter, and the company expected trucking of that material to finish during calendar 2026.
Trident and Old Highway schedules
Longer-term guidance issued in September 2025 had contemplated 130,000 to 150,000 ounces in FY27 and included production from Old Highway and Trident. In the updated schedule, permitting delays moved expected Old Highway production into the following financial year. At Trident, the company cited a delayed underground start and slower development progress. Grade-control drilling improved the overall resource grade but did not produce comparable improvements at the outer portions of the deposit.
Underground development at Trident continued, with crews starting day and night shifts. Catalyst commenced grade-control drilling at the Old Highway open pit during the quarter and at Cinnamon after quarter-end. The company said it would prioritise development work to separate mine development areas from production areas before proceeding with output from new underground sources.
Spending and liquidity
Catalyst recorded AUD 80 million of Operating Cash Flow after sustaining capital, corporate costs and working Capital movements. It allocated AUD 13 million to growth projects, AUD 10 million to non-discretionary capital and AUD 17 million to exploration. Those outlays left a quarterly increase of AUD 40 million in cash and bullion.
The revolving credit limit increased from AUD 100 million to AUD 200 million and was extended to four years. The facility was undrawn at quarter-end, and Catalyst reported Liquidity of AUD 571 million. FY27 expenditure guidance included AUD 30 million to AUD 40 million for non-discretionary, non-recurring capital and AUD 70 million to AUD 80 million for discretionary growth capital. Exploration spending was guided at AUD 80 million to AUD 90 million. The growth budget set aside AUD 25 million to AUD 30 million for equipment and AUD 38 million to AUD 42 million for Trident, with a separate allocation for other growth projects.
Longer-term production plans
The filing reported an ore reserve of approximately two million ounces and retained a longer-term production target of around 200,000 ounces a year. Catalyst said it was still assessing the implications of reorganising the near-term production schedule and expected output to vary across FY27. The company identified processing plant work, new tailings capacity and Trident underground development among its spending priorities.