  • Black Bear Minerals (ASX:BKB) reported higher silver grades in selected historical drill intervals at Shafter.
  • One retested interval averaged 1,043 grams of silver per tonne over 9.1 metres versus 801 grams per tonne originally.
  • Black Bear began planning its first underground drilling program at Shafter during the September quarter.
  • Its Independence scoping study evaluated open pit Mining and heap leaching in Nevada.

Black Bear Minerals (ASX:BKB) used its September 2026 Quarterly Report to present laboratory results from older Shafter drill core and describe preparations for underground exploration at the Texas silver project. The 29 October release also recorded the final results of a surface drilling campaign received after quarter-end and summarised a preliminary mining study for the Independence Gold Project in Nevada.

Retesting historical Shafter intervals

The company resampled core from past drilling as part of a program to validate Shafter’s resource data. Initial results received during the quarter covered material from historical surface and underground diamond drilling. In hole 201200604, an 8.5-metre interval from the start of the hole averaged 525 grams of silver per tonne in the new analysis, against 493 grams per tonne in the original results.

In hole 201200106, a 14.6-metre interval starting at 64.6 metres averaged 542 grams of silver per tonne, compared with 471 grams per tonne historically. Within that interval, 6.7 metres averaged 1,038 grams per tonne, up from 932 grams per tonne. A separate 7.9-metre interval in hole S-12-406 averaged 377 grams per tonne, against the original 250 grams per tonne. The comparisons use matching downhole intervals.

The program also measured gold. Hole 201200609 returned 6.1 metres averaging 0.5 grams of gold and 227 grams of silver per tonne. That section included 1.2 metres at 1.9 grams of gold and 36 grams of silver per tonne. Black Bear also compiled historical results that showed gold alongside silver in selected intersections.

Surface and underground exploration

The company had drilled 6,311.8 metres at Shafter when it reported, covering extension drilling, holes paired with older drilling for validation and holes to test the local rock sequence. One southern hole, SFD027, intersected the Mina Grande Formation beneath younger cover. It recorded no significant silver mineralisation. Black Bear said the geological information would help it plan follow-up work to the south.

The planned underground program focuses on areas reachable from existing development, including Presidio East and the Ramp area. It will test for extensions within and beyond the existing foreign mineral resource estimate. Black Bear identified about one kilometre of strike around the Presidio workings where remaining mineralisation falls outside that estimate. Site readiness work was underway ahead of access to the existing decline. The company reported about AUD 7.82 million of cash at 30 September, compared with AUD 5.17 million at the start of the quarter. The planned underground drilling would complement further surface work.

Independence mining study

An August scoping study evaluated contract mining by open pit and heap leaching for near-surface mineralisation at Independence. It used a portion of the May 2026 mineral resource estimate. The study modelled processing about 9,000 tonnes daily and used a production target of 31.9 million tonnes at 0.30 grams of gold and 6.09 grams of silver per tonne. Approximately 73% of the target was drawn from indicated resources and 27% from inferred resources. The proposed mine life of 9.7 years was a study estimate.

Next steps for Shafter

The October update identified underground access and resource definition as the next stages at Shafter. Black Bear planned to use new geological information from underground and surface drilling to support conversion of the foreign estimate to reporting under the JORC Code. The retesting campaign supplies verification data for that work, while the Independence report outlines a separate development concept at scoping-study stage.