Key Highlights

  • Maritana Minerals (ASX:MRT) reported assays from the last 52 holes of the 119-hole Boorara reverse circulation programme.
  • Infill hole BOORD260054 returned 20 metres at 7.77 grams of gold per tonne from 100 metres downhole.
  • A hole drilled down plunge beneath Pit 4 returned 36 metres at 3.53 grams of gold per tonne.
  • Maritana scheduled an updated Boorara mineral resource estimate for the March 2027 quarter.

Maritana Minerals (ASX:MRT) reported the final reverse circulation assays from a resource definition and extension programme at its wholly owned Boorara Gold Project on 5 November 2026. The Western Australian site is about 17 kilometres east of Kalgoorlie-Boulder. Drilling concentrated on the main contact lodes between existing pits and assessed how far mineralisation extends below the planned southern pit.

Infill drilling between Boorara pits

The infill component concentrated largely between recently mined Pits 2 and 4, with extension holes north of Pit 2 and down dip of Pit 4. Surface drill holes generally ran southwest to cut across mineralisation along steep geological contacts, shallower veins in the footwall and networks of quartz veins. Maritana said the new results helped it refine the boundaries of the main contact lodes.

The 20-metre interval in BOORD260054 included two metres at 54.04 grams of gold per tonne from 114 metres. Hole BOORD260056 returned 19 metres at 1.63 grams per tonne from 108 metres, including one metre at 5.25 grams per tonne. Another hole, BOORD260119, returned 10 metres at 1.67 grams per tonne from 30 metres, including one metre at 9.08 grams per tonne.

Testing depth beneath Pit 4

Maritana drilled BOORD260149 down the plunge of mineralisation beneath Pit 4. The 36-metre intersection began at 142 metres and included one metre at 62.44 grams of gold per tonne from 156 metres. The same hole returned 20 metres at 1.75 grams per tonne from 34 metres, including two metres at 5.62 grams per tonne from 52 metres. The company’s cross-section showed the deeper intersection about 80 metres below the designed pit shell. The two oriented extension holes were also designed to gather information on gold distribution and the orientation and density of the veins within the mineralised zones and dolerite-hosted contact lode.

A second extension hole, BOORD260148, was drilled down dip south of Pit 2. It returned 12 metres at 1.28 grams of gold per tonne from 12 metres, including one metre at 5.09 grams per tonne. Maritana specified that the reported lengths for those two holes are downhole intersections because of their orientation. They should be read as lengths along the drilled paths.

Mine planning and the Black Swan hub

Boorara comprises the Royal, Regal and Crown Jewel deposits over approximately 1.5 kilometres of strike on granted Mining leases. The site entered care and maintenance after mining stopped in December 2025 at the end of the previous ore purchase agreement. Maritana identified Boorara as one of the principal planned ore sources over the life of its Black Swan Processing Hub.

The company expected pre-production planning, site layout work and grade-control drilling ahead of the targeted restart in mid-2027. It also reviewed whether to redrill or re-enter two holes that ended early after drill conditions deteriorated and the holes deviated. Maritana said it did not expect those two holes to materially affect the pending resource update.

Next steps for the resource estimate

The Boorara work formed part of a roughly 60,000-metre resource conversion campaign across several deposits. Maritana planned to incorporate the new assays into its March 2027 quarter resource update, with further pit optimisation to follow. The company also planned additional diamond drilling to check mining assumptions and support quality control before the scheduled restart.