Key Highlights
- Vulcan Energy (ASX:VUL) completed drilling at Lionheart’s seventh well during the September 2026 quarter.
- The first two strategic Equity drawdowns brought in EUR 53.7 million, and initial grant receipts totalled EUR 10.7 million.
- Civil construction commenced at the 30-megawatt geothermal power plant site.
- Vulcan completed a preliminary feasibility study for Project Ludwig, its proposed second development phase.
Vulcan Energy (ASX:VUL) reported progress on the wells, pipelines and processing facilities for its Lionheart lithium and geothermal project in Germany in the quarter ended 30 September 2026. The 30 October update included early payments under its funding package and the results of a reinjection test completed after quarter-end. Vulcan also reported that project drilling and construction were proceeding on schedule and within budget.
Lionheart wells and brine reinjection
Lionheart’s field plan calls for production wells that bring hot, lithium-bearing brine to the surface for Geothermal Energy and lithium extraction. Reinjection wells return the lithium-depleted brine underground. Drilling on the seventh well, a reinjection well, included a pilot hole and a horizontal sidetrack. Drilling finished during the quarter.
Testing after 30 September showed that the sidetrack could inject brine into the sandstone reservoir matrix. Vulcan said the test provided direct field evidence supporting its subsurface assumptions. At the Trappelberg site, foundations for the drilling rig were nearing completion while the inner pad remained under construction. Vulcan had refurbished its second onshore rig and planned to begin moving it to Trappelberg in the fourth quarter of 2026.
Pipelines and processing facilities
Construction began on the first section of the pipeline and power package, which connects the wells with the geothermal and lithium extraction facilities. Vulcan targeted completion of the first section in the third quarter of 2027. Preparations continued for the second section, with construction scheduled to begin in the fourth quarter of 2026. The company had received tenders for sections three to seven, with awards expected in the same quarter.
Early bulk earthworks for the lithium extraction plant were complete, along with relocation of a 110-kilovolt overhead line. At the geothermal power site, civil work covered foundations, roads and structures for air-cooled condensers. Both the lithium extraction plant and Downstream chemicals plant had completed their 30% design reviews, and the project team was working towards the 60% reviews. Early civil work and engineering continued at the downstream site.
Equity drawdowns and production preparations
Vulcan received its first two strategic equity payments under Lionheart’s EUR 2.2 billion funding package after meeting relevant milestones. The German government also began making grant payments. During the quarter, Vulcan started commercial-scale production of its lithium extraction adsorbent, VULSORB, to provide the initial charge for the extraction columns ahead of commissioning.
At demonstration scale, the Upstream optimisation plant produced a lithium chloride solution. Vulcan transferred it to the downstream optimisation plant to make battery-grade lithium hydroxide monohydrate. The company said continued operation of those facilities supported financing and other stakeholder milestones. The Mining authority in Rhineland-Palatinate issued an additional lithium production licence, designated Ilka, in the Upper Rhine Valley Brine Field.
Vulcan reported EUR 88.8 million of development expenditure during the quarter, primarily for Lionheart. Of that total, EUR 22.7 million went to Supply and installation of the geothermal power plant equipment. The upstream extraction plant accounted for EUR 25.5 million, and the downstream chemicals plant accounted for EUR 13 million.
Next stages for Lionheart and Ludwig
Lionheart remained Vulcan’s main construction project in the September update. Project Ludwig had reached preliminary feasibility study stage as a proposed second phase of lithium and geothermal energy production. That study assumed a 30-year operating life. For Lionheart, the construction schedule called for further pipeline work, design reviews and mobilisation of the second rig, alongside preparation of material for the extraction columns.