Key Highlights

  • Minbos Resources (ASX:MNB) drew approximately AOA 1.97 billion, equivalent to about USD 2.2 million, under its Angolan construction facility.
  • A separate USD 2.8 million funding claim submitted to South Africa’s Industrial Development Corporation remains subject to the facility’s requirements.
  • The initial Cácata Mining campaign placed 23,495 tonnes of phosphate rock on an on-site stockpile for planned plant commissioning.
  • Minbos retained its second-quarter 2027 commissioning target while reporting that fabrication work in Portugal was nearing completion.

Minbos Resources (ASX:MNB), which is developing the Cabinda Phosphate Project in Angola, has made the first drawdown from its Banco de Fomento Angola construction facility. The 23 November 2026 update also reported completion of the initial mining campaign at Cácata, progress at the Subantando beneficiation plant and preparations for Marketing the project’s fertiliser.

Two Debt facilities at different stages

The first drawdown took place on 18 November under a Banco de Fomento Angola Facility of AOA 5 billion. Minbos reported that the AOA 1.97 billion drawdown was made to Soul Rock Limitada and applied directly to construction contractors and suppliers. Minbos gave an approximate US dollar equivalent of USD 2.2 million for the project’s first construction facility drawdown. The facility is earmarked for construction.

The company filed a second utilisation claim under its existing facility with the Industrial Development Corporation of South Africa on 11 November. Minbos put the claim at USD 2.8 million and said the drawdown remained subject to the applicable facility requirements. It also reported that it had received no significant contract variations and that it did not expect any. The two updates describe a completed drawdown under the Angolan facility and a separate claim under the South African facility.

Mining provides initial feedstock at Cácata

The initial campaign ended on 31 October, and the contractor demobilised on 2 November. The scope included building access roads, clearing the site and removing topsoil. Crews then stripped overburden and extracted phosphate rock. Minbos said the material was placed on a run-of-mine stockpile at Cácata after extraction.

The 23,495 tonnes form the initial phosphate inventory for the project. Minbos intends to use the stockpiled rock to feed the Subantando beneficiation plant during commissioning. The inventory is held at the mine’s run-of-mine stockpile pending commissioning. Minbos reported that the material would support commissioning at the beneficiation plant in line with its previously announced development programme. It identified the stockpile as phosphate rock rather than processed fertiliser.

Plant construction and fertiliser field trials

Minbos said fabrication in Portugal was nearing completion. At the Subantando site, representatives of Stelo and the Industrial Development Corporation inspected processing infrastructure and reviewed construction progress. The company said the visit also included discussion of the project’s next stages. The schedule continued to target commissioning in the second quarter of 2027.

Seven large field trials were progressing with established farms to test the company’s granulated fertiliser. Minbos also appointed Corentin Rault as marketing and sales manager from 23 November. The company noted his experience with phosphate rock and its use in fertiliser manufacturing. The appointment accompanies work on how Minbos plans to bring the fertiliser to market.

Cabinda’s next milestones

The company has completed initial mining and put the first Angolan facility proceeds towards construction counterparties. Work remains on the plant, with fabrication nearing completion and commissioning still scheduled as a target. The second debt claim remains contingent on the facility requirements. Minbos identified outstanding contractual and regulatory arrangements, weather and funding among factors that could affect future project progress. Those factors also apply to the schedule for commissioning, which remained a target in the November release. The company separately flagged uncertainties around potential local market Supply and production. The continuing field trials are focused on the granulated fertiliser as plant construction proceeds.