- Axel REE (ASX:AXL) appointed WSP Australia to lead technical studies, design, planning and execution of its first Woolrich in situ recovery field programme.
- Detailed auger drilling is underway across a two-hectare study area to refine the geological model and obtain samples for leach tests.
- Axel plans to combine drilling data with magnesium sulphate leach results from SGS to select the location for the field work.
- An earlier Woolrich laboratory programme produced mixed rare earth carbonate containing 54.4% total rare earth oxides using column leach solutions.
Axel REE (ASX:AXL), the owner of the Caladão Rare Earth Elements and Gallium Project in Brazil, has engaged WSP Australia to lead field testing at the Woolrich deposit. The company’s 23 November 2026 announcement also confirmed that auger drilling had started within the area being considered for the first in situ recovery programme.
WSP’s scope for the first Woolrich field programme
WSP’s assignment extends from specialist studies and design to planning and execution. The company said WSP had relevant in situ recovery field testing experience in Brazil. Its work will incorporate hydrogeological investigations and may include geotechnical studies. Those investigations will inform how the field programme is designed and carried out.
The planned test will examine the behaviour of magnesium sulphate as a leaching solution in the mineralised regolith. It will look at how the solution moves through the material and how it can be contained hydraulically. The programme also covers the recovery of the solution carrying dissolved rare earths. Axel intends to use site measurements in designing future wellfields and evaluating possible larger-scale operations.
Drilling and assays will guide site selection
Axel began detailed auger drilling within the designated two-hectare study area. The drilling is intended to refine geological details of the rare earth mineralisation in the regolith. It will also provide additional samples for SGS to test using magnesium sulphate. Axel plans to use the geological information and leach assays together when choosing the precise field test location.
Drilling and the WSP work are progressing in parallel. Axel said the drilling results would inform the design as well as the location of the field programme. The tests use site samples to support selection of a representative location within the study area. The company’s immediate priorities include completing the drilling and combining the available evidence before confirming the location.
What the laboratory work established
Axel’s October laboratory update reported a mixed rare earth carbonate product made from solutions collected during column leach tests. The carbonate contained 54.4% total rare earth oxides. The November update cited that result as the preceding metallurgical work for the proposed field programme. The work at Woolrich now aims to evaluate the magnesium sulphate process in a controlled field setting.
Woolrich forms part of the wholly owned Caladão project in Minas Gerais. The company has identified field measurements that will focus on solution movement, containment and collection. Axel lists Woolrich as one of four rare earth deposits at Caladão and its priority for this recovery method. The Woolrich mineral resource stands at 264.6 million tonnes at 1,101 parts per million total rare earth oxides, including approximately 110.1 million tonnes in the indicated category at 1,073 parts per million. The combined mineral resource across the four deposits is 708.6 million tonnes at 1,443 parts per million. The company reported the updated Woolrich estimate in September 2026.
Steps before the field programme proceeds
Axel plans to finish detailed drilling, receive and incorporate the SGS results, and settle on a test location. WSP’s specialist investigations will advance alongside preparation of the field design. The announced work is intended to assess whether the recovery process can be applied at a larger scale at Woolrich. The November release did not set a date for completing the field test.