Key Highlights
- Prairie Lithium (ASX:PL9) recovered brine from its Saskatchewan production well after re-entering the well and completing perforation and swabbing work.
- The recovered brine is earmarked for further metallurgical tests, following completion of the initial production test targeted for the fourth quarter of 2026.
- Contouring and grading expanded the Pad 1 working area to make room for additional infrastructure needed for Phase 1.
- Interest-free Canadian government financing of CAD 6.3 million is intended to support procurement and installation of Phase 1 processing equipment and supporting systems.
Prairie Lithium (ASX:PL9), which is developing a lithium brine project in Saskatchewan, Canada, has brought brine to the surface at its first project production pad. The 23 November 2026 update also confirmed completion of civil works at Pad 1, where the company is preparing to install and connect additional infrastructure for the initial stage of development.
How the Pad 1 well test was carried out
Prairie Lithium mobilised a local service rig to re-enter the production well. The work focused on completing production zones within the Duperow Formation through perforation and swabbing. The programme brought brine to the surface and satisfied the initial brine production testing milestone identified in the company’s September 2026 quarterly activities report. The Quarterly Report had scheduled the milestone for the final quarter of the calendar year.
The brine collected in the programme will be used in continued metallurgical testing. That work is listed separately among the company’s next priorities alongside work on site infrastructure. The project is located near existing power, natural gas, fresh water, highways and railways, according to the company. The development plan includes continued work on lithium extraction and concentration before Phase 1 processing infrastructure is in place.
Groundworks prepare space for equipment
Site crews completed work to extend the operating area and contour and grade the ground at Pad 1. The expanded area is intended to accommodate equipment and related infrastructure for Phase 1. Prairie Lithium completed the well intervention and site preparation ahead of the Canadian winter, according to the company. Earlier work at the pad included completion of the production and disposal wells, power infrastructure and the Facility building.
A four-column commercial-scale direct lithium extraction unit has already arrived. Further work includes preparations for the unit’s associated systems, including pre-treatment and lithium chloride concentration. Management also listed procurement and installation planning for Phase 1 processing equipment and balance-of-plant systems. The company is preparing to install and connect new infrastructure within the expanded site area.
Government financing and Phase 1 offtake
The project has been approved for CAD 6.3 million in interest-free Canadian government financing through Prairies Economic Development Canada. The funding is intended for the procurement and installation of processing equipment and supporting Phase 1 systems. On the commercial side, Prairie Lithium has a binding offtake agreement with Hydro Lithium covering 100% of planned Phase 1 production. The offtake applies to planned output from the first phase of the staged project. Prairie Lithium described the agreement as binding in its update, alongside the government financing and the delivery of the extraction unit. The company had previously reported the offtake in April and approval of the Canadian financing in September 2026.
What Prairie Lithium is working on next
The company’s next work combines tests on the recovered brine with preparations for equipment procurement, installation and integration. Management said it would continue to assess the pace and timing of development against funding availability, project requirements and lithium market conditions. Its stated focus is on construction activities that determine the project schedule while managing expenditure. The November update also listed ongoing preparation for pre-treatment and concentration systems among the priorities following completion of the site expansion and well programme.