Key Highlights

  • Kantra Copper (ASX:KAN) approved Phase 2 of the Coburn prefeasibility study after reviewing the logistics and metallurgical work completed in Phase 1.
  • The preferred rail siding near Cockburn township is approximately 20 kilometres from Coburn and would connect to the project by road.
  • Kantra lifted its 2026 major Capital Expenditure guidance to AUD 18.5 million to AUD 19.5 million to incorporate Phase 2 spending.
  • The company had drilled six holes totalling 1,318 metres by 20 November 2026, with logging underway and results pending.

Kantra Copper (ASX:KAN), which operates the Kanmantoo copper operation and is studying Coburn as a potential source of mill feed, has approved the second phase of its Coburn prefeasibility study. The 23 November 2026 announcement described a road and rail concept and raised capital expenditure guidance to account for the next phase.

The road and rail concept for Coburn

The Phase 1 logistics study examined the transport of mineralised material from Coburn to Kanmantoo for processing, using road haulage for the first leg. Kantra said the study identified a commercially viable pathway. Its preferred concept includes a rail siding near Cockburn township and an indicative road corridor between Coburn and that siding. The siding is approximately 20 kilometres from the project, and the concept at Cockburn includes a rail balloon loop connected to existing infrastructure.

At the other end of the route, Kantra is considering a new siding and rail loop next to the Kanmantoo processing plant. The team estimates transport costs at about five to seven Australian cents per tonne per kilometre. It plans to test and refine that estimate during Phase 2. The detailed road and rail designs are subject to community consultation and regulatory approval.

Phase 2 studies and capital guidance

The board reviewed the logistics study alongside metallurgical test work reported in October 2026. Kantra had identified metallurgy and logistics as material issues during due diligence. Following the Phase 1 work, the board approved the next stage of technical assessment. Management said about 18 months of prefeasibility work remained before it could make a final Investment decision.

Kantra expects total Coburn prefeasibility spending of approximately AUD 11 million to AUD 13 million, including AUD 970,000 spent through the end of October. The company separately increased its 2026 major capital expenditure guidance to reflect spending on Phase 2. The next study stage will cover mine design, processing configuration, infrastructure requirements, the transport route, regulatory approvals and project economics.

Drilling and electromagnetic work at Coburn

Kantra designed the first eight holes to support further metallurgical tests, geochemical characterisation and checks on geological domains. It was logging the completed holes when it issued the update. Following initial verification drilling, the company plans to target areas that can improve geological confidence and support future geological studies. It then plans to evaluate opportunities to extend the resource in 2027. The drilling update provided a progress total, with results still pending.

Kantra also completed a surface electromagnetic survey to help identify the mineralised structure along strike and at depth. Data processing and interpretation are the next steps for that survey. The company expects to use the results to refine the targets and designs of later drill holes. This work sits alongside the assessment of mine design and processing options.

What remains before a development decision

Kantra is examining Coburn as a possible source of future feed for the Kanmantoo plant. The work that remains covers geology, engineering, logistics, approvals and economics. Phase 2 includes further assessment of the road and rail infrastructure and testing of the cost assumptions used so far. Management said its immediate operating focus remains delivery of Kanmantoo’s 2026 production and cost guidance.