Key Highlights

  • Scarborough and Pluto Train 2 were 99% complete at the end of September, excluding modifications to Pluto Train 1.
  • Woodside kept its Q4 2026 target for Scarborough’s first LNG cargo at its November Capital Markets Day.
  • Louisiana LNG was 32% complete at the end of September, with Train 1 at 41% and first LNG targeted for 2029.
  • A 20-year QatarEnergy agreement covers up to 3 million tonnes of LNG annually, with deliveries starting when Train 2 starts up.

Woodside Energy (ASX:WDS) is heading into 2027 with its two LNG developments at different stages. At Scarborough in Western Australia, the company had introduced gas into Pluto Train 2 for pre-treatment and continued to target a first cargo in late 2026. At Louisiana LNG, work was under way across all three trains, with first LNG targeted for 2029.

Scarborough gas reaches Pluto Train 2

Woodside produces and sells oil and gas, including liquefied natural gas. Scarborough links an offshore gas field to the existing Pluto LNG site. Woodside reported that Scarborough and Pluto Train 2 were 99% complete at 30 September and remained on budget. That percentage excluded modifications to Pluto Train 1, which are designed to allow the existing train to process Scarborough gas as well.

During the September quarter, Scarborough gas entered the floating production unit and was sent into the trunkline. Woodside completed mechanical runs of the Train 2 compressors and said gas reached the train’s pre-treatment section after quarter-end. The company was still working on the section that cools the gas into liquid form. The final module for the Train 1 modifications had arrived on site, where crews were connecting it to the existing facilities.

Louisiana construction advances across three trains

Woodside reported that Louisiana LNG, near Lake Charles, was 32% complete at the September quarter-end and remained on budget. Train 1 reached 41% completion as installation of structural steel and above-ground piping advanced. Train 2 was 27% complete and had begun above-ground piping installation. Train 3 was 22% complete, with the first concrete poured for its foundation.

Work also continued on the terminal’s marine facilities, site works and storage tanks. Woodside reported that concrete work on the walls of the first LNG tank had reached 50%. It also reported challenges with structural steel Supply linked to disruption in the Middle East and said it was using alternative transport routes and fabrication sources. The three trains are designed for a combined capacity of 16.5 million tonnes a year.

How the QatarEnergy agreement fits the schedule

Woodside announced a 20-year sale and purchase agreement with QatarEnergy on 29 October. Deliveries are scheduled to begin when Louisiana LNG’s second train starts operating and to rise to 3 million tonnes a year from the start-up of Train 3. Woodside will supply that LNG from its own share of project volumes. The deal is on a free-on-board basis, with the buyer arranging onward shipping from the loading terminal.

The QatarEnergy contract follows an earlier agreement with Uniper. Its staged deliveries link the sales volumes to the commissioning of the later trains. For 2027, the two projects have different milestones to track. Scarborough’s next step is to move from commissioning into shipments and ramp-up, while Louisiana’s progress can be measured through construction across the trains and terminal ahead of its 2029 target.