Highlights
- Northern Star (ASX:NST) sold 363,891 ounces of gold at an AISC of A$3,217 an ounce in the September 2026 quarter.
- FY27 guidance of 1.50–1.65 million ounces at A$3,050–3,450 an ounce was unchanged.
- Tie-in of the expanded KCGM mill was completed on 28 September 2026.
- Cash and bullion were A$1.2 billion, with corporate bank facilities increased to A$2.25 billion.
- A final Investment decision on the Hemi project is still targeted for late FY27.
Northern Star Resources Limited (ASX:NST) reported gold sales of 363,891 ounces for the September 2026 quarter, a period in which it shut down the legacy plants at its KCGM operation in Kalgoorlie and tied in the expanded mill. The report, released on 21 October, kept FY27 guidance unchanged and said production is expected to be weighted to the second half as the expanded plant ramps up.
Quarterly Production and Costs
All three production centres were cash positive. Kalgoorlie sold 193,540 ounces at an AISC of A$2,919 an ounce, Yandal sold 117,631 ounces at A$3,687 an ounce and Pogo in Alaska sold 52,720 ounces at US$2,307 an ounce. Net mine Cash Flow was A$210 million, but underlying free cash flow was negative A$31 million after A$113 million of corporate tax payments. Northern Star (ASX:NST) said grade and recovery impacts from commissioning at KCGM and Pogo reduced gold sold and lifted costs relative to the June quarter.
KCGM Mill Expansion
The legacy KCGM plants were shut down on 21 September and the tie-in to the expanded plant was completed on 28 September. Early commissioning temporarily reduced milled tonnes, grade and recovery. Stage II commissioning is scheduled for early in the second half of FY27 and is expected to lift recovery by 1–2% and remove concentrate haulage between KCGM and Gidji. Quarterly Capital Expenditure on the project and readiness was A$221 million, and total project spend to date was A$1.746 billion against a forecast of A$1.75–1.81 billion. Northern Star (ASX:NST) noted that production, recovery and throughput assumptions will be informed by operating experience.
Hemi, Hedging and Funding
Engineering, design and permitting at the Hemi project in Western Australia are progressing, managed aquifer recharge trials began, and a final investment decision remains targeted for late FY27. The company expects Hemi-related tax Depreciation to create cash tax savings of about A$300–350 million in FY27 and A$200–250 million in FY28. Cash and bullion were A$1.2 billion at 30 September, corporate facilities were increased to A$2.25 billion, and A$500 million was drawn on 9 October ahead of the FY26 final Dividend payment. Hedging deliveries were 140,000 ounces, leaving 647,500 ounces committed. Exploration spend was A$56 million.
Leadership and Risks
Suresh Vadnagra commenced as Managing Director and CEO on 5 October 2026. The main variables for Northern Star (ASX:NST) are the speed of the KCGM ramp-up, grades and recoveries across the three centres, cost performance against the guidance range and the Hemi decision. The group safety measure was 0.5 injuries per million hours worked.
Key Insights
Northern Star (ASX:NST) is in a commissioning phase at its largest operation, which reduced the quarter's output and raised unit costs. The company's disclosures show unchanged guidance weighted to the second half, so the performance of the expanded KCGM mill is the central item to follow.