Highlights

  • Fortescue (ASX:FMG) shipped 46.8 million tonnes in the September 2026 quarter, including 2.5 million tonnes from Iron Bridge.
  • Sales were 42.9 million tonnes, reflecting ongoing negotiations with China Mineral Resources Group.
  • Net Debt rose to US$2.8 billion after a US$1.0 billion final Dividend and Capital spending.
  • FY27 shipment guidance of 197–207 million tonnes is subject to the negotiation outcome.
  • The company reported a maiden Ore Reserve at Blacksmith and first hot metal from its Green Metal Project.

Fortescue Ltd (ASX:FMG) reported September 2026 quarter shipments of 46.8 million tonnes, 6% lower than a year earlier, while sales of 42.9 million tonnes lagged shipments by 3.9 million tonnes. The company linked the gap to ongoing negotiations with China Mineral Resources Group, and said that if talks are not concluded by calendar year-end its operations may be affected, potentially including production adjustments.

Shipments, Costs and Guidance

Shipments comprised 44.3 million tonnes of hematite and 2.5 million tonnes of Iron Bridge concentrate, 11% below the June quarter. Fortescue (ASX:FMG) said product inventory is expected to rise by a further 4–5 million tonnes in October as it optimises product placement. The hematite C1 unit cost was US$21.98 a wet metric tonne, up 13% on the previous quarter, with higher diesel adding about US$1.40 a tonne compared with a year earlier. FY27 guidance is unchanged at 197–207 million tonnes, including 11–14 million tonnes from Iron Bridge, with a hematite C1 cost of US$20.50–21.75 a tonne.

Cash, Debt and Capital Spending

Cash was US$3.2 billion at 30 September, down from US$5.1 billion at 30 June, and gross debt was US$6.1 billion, leaving net debt of US$2.8 billion, up from US$0.9 billion. Quarterly outflows included the FY26 final dividend of US$1.0 billion and US$916 million of Capital Expenditure and investments. FY27 metals capital expenditure guidance is US$3.7–4.7 billion, and energy capital expenditure is about US$150 million. The company completed its largest-ever port shutdown during the quarter, with further life-cycle maintenance planned for FY28–29.

Decarbonisation and Growth Projects

Fortescue (ASX:FMG) reported 21 electric excavators operating in the Pilbara and first turbine components arriving for the 133-megawatt Nullagine Wind Project. The Green Metal Project produced first hot metal at Christmas Creek using its electric smelting process, and in October the company sold more than 40 tonnes of copper concentrate cleaned using the Toowong Process. At Blacksmith, the Mineral Resource rose 153% to 615 million tonnes, with a maiden Ore Reserve of 196 million tonnes at 58.0% iron. More than 250,000 metres have been drilled at the Belinga project in Gabon, and copper exploration is active in several countries.

Risks and Watch Points

The main risk is the outcome of the negotiations, which could affect sales volumes, inventory and production. Other variables for Fortescue (ASX:FMG) include diesel costs, the ramp-up of Iron Bridge, in which it holds a 69% Equity share, and capital allocation across its metals and energy programs. The company also released its 2026 Climate Transition Plan during the quarter.

Key Insights

Fortescue (ASX:FMG) shipped more than it sold in the September quarter, and the gap was attributed to ongoing contract negotiations. The company's disclosures show rising net debt and a conditional full-year guidance range, so the conclusion of the talks and the pace of inventory movements are the key items to follow.