Highlights

  • Chalice Mining (ASX:CHN) held A$53 million in cash and listed investments at 30 September 2026, with no borrowings.
  • A definitive feasibility study for Gonneville is expected in the third quarter of calendar 2027.
  • A final Investment decision is targeted for the first half of calendar 2028.
  • Environmental review submissions to state and federal regulators are due in the fourth quarter of 2026.
  • First-pass drilling at Deep Blue found broad, low-grade copper-silver-gold zones.

Chalice Mining Limited (ASX:CHN) is advancing its 100%-owned Gonneville project in Western Australia through approvals and feasibility work, with a final investment decision targeted for the first half of calendar 2028. The company's September 2026 quarterly report, released on 27 October, set out a timetable of regulatory submissions, a pilot plant campaign and offtake negotiations, alongside a cash position of about A$53 million.

The Gonneville Project

Gonneville is a platinum group metals, nickel, copper and cobalt project in Western Australia. The pre-feasibility study, completed in December 2025, modelled a two-stage open-pit mine producing about 220,000 ounces a year of platinum, palladium and gold, with 7,000 tonnes of nickel, 8,000 tonnes of copper and 700 tonnes of cobalt, over 23 years. The company reported an Ore Reserve of 7.1 million ounces of platinum, palladium and gold. These are study outputs and depend on assumptions that may change. Chalice (ASX:CHN) is now preparing a definitive feasibility study due in the third quarter of calendar 2027, and an eight-week continuous pilot plant campaign using about five tonnes of ore begins in November 2026.

Approvals, Funding and Offtake

Approvals are described as the critical path. The Environmental Review Document and Public Environment Report are due for submission in the fourth quarter of 2026, and mining Lease applications are expected in the first quarter of 2027. An independent review by a former chair of the state environmental regulator endorsed the approvals strategy and the targeted timetable, with first production expected in early 2030. Chalice (ASX:CHN) is targeting 60–70% of pre-production funding from export Credit agencies, sovereign Debt or grants, and formal negotiations on copper and nickel concentrate offtake have started with interested smelters in several countries.

Exploration and Corporate

At Deep Blue, part of the Goomalling copper project, 16 reverse circulation holes totalling 1,874 metres intersected broad copper-silver-gold zones over 1.2 kilometres of strike, including 21 metres at 0.18% copper from 50 metres. The company describes the zones as low grade and open along strike, and the source of high-grade rare earth rock chips has not been found. Next steps include a geophysical survey and extended soil sampling. A A$5 million contingent payment is expected on commercial production at the Nyanzaga gold project in Tanzania, with first production expected in early 2027.

Cash and Board Changes

Cash was about A$44.7 million and listed investments about A$8.2 million at 30 September, with a quarterly net outflow of about A$6.7 million and no debt facilities. Chalice (ASX:CHN) also reported a planned chair succession, with Ross Carroll to succeed Derek La Ferla after the 20 November annual general meeting, subject to Shareholder approval. The key risks are approvals timing, study outcomes, financing and the early stage of the exploration targets.

Key Insights

Chalice Mining (ASX:CHN) has a long development timetable at Gonneville, with feasibility work, approvals and financing still to be completed. The company's disclosures show a sizeable cash position and no debt but no committed project funding, so regulatory decisions and the feasibility study are the key milestones.