Highlights
- BHP (ASX:BHP) presented its South Australian copper development strategy during a site tour in November 2026.
- The strategy identifies potential annual copper production of approximately 500,000 tonnes by 2035 and 650,000 tonnes by 2040.
- The first phase includes mine development alongside a proposed expansion of smelting and refining infrastructure.
- The development Options have different levels of technical Maturity and remain subject to further assessment and Investment decisions.
BHP (ASX:BHP) is a diversified resources group with operations spanning commodities such as copper and iron ore. Its South Australian copper Business brings together underground mines and processing infrastructure. The November 2026 site tour outlined how successive investments could increase production over the coming years, with individual projects following separate development schedules.
Copper Output Milestones to 2040
The company's strategy envisages a first phase of investment supporting annual copper production of approximately 500,000 tonnes by 2035. A subsequent phase could lift that figure to around 650,000 tonnes by 2040. These are prospective output levels, rather than current production figures or unconditional commitments to develop the projects.
Copper production is distinct from copper-equivalent production, which incorporates the contribution of other commodities using specified assumptions. This distinction is particularly relevant to Olympic Dam, where the ore contains several metals. The development programme therefore involves decisions about both the Volume of material mined and the configuration of the processing facilities needed to recover saleable products.
Underground Development Across the Copper Province
At Prominent Hill, the shaft expansion is intended to replace truck haulage with shaft hoisting. The November presentation identified commissioning in the second half of calendar 2026 and a forecast final cost of USD 900 million. The change in haulage arrangements forms part of the broader mine development programme.
At Carrapateena, the proposed expansion involves establishing a block cave approximately 450 metres below the current sublevel cave. Indicative Capital Expenditure is USD 1.8–2.1 billion, with a possible investment decision in the first half of calendar 2028. Potential first production is identified for FY30. Block caving enables large volumes of underground material to be extracted, but its deployment requires substantial preparatory work before ore can be delivered to processing facilities.
Olympic Dam Mine and Processing Investment
The Olympic Dam mine and concentrator growth project is intended to establish a block-caving platform and expand the use of the existing resource. Its indicative investment requirement is USD 4.1–5.4 billion, with a possible decision in calendar 2029 and potential first production in FY34.
The associated smelter expansion is estimated at USD 3.2–4.1 billion, with a possible final investment decision in the second half of calendar 2027. Potential first production is identified for FY32. The planned smelting configuration is designed to accommodate concentrate from the wider copper province, while some remaining concentrate could be sold externally. The final capacity of the Facility remains subject to an investment decision.
Project Sequencing and Execution Considerations
Capital estimates in the November presentation are expressed in real terms as at 1 July 2026 and exclude certain commercial infrastructure commitments. They therefore should not be treated as fixed construction budgets. The timing of individual investments also matters because additional mine output must be matched with transport and processing arrangements.
Projects remain at different stages of assessment. Construction costs, engineering requirements and operational performance will influence the eventual production profile. The later phase provides another avenue for increasing output, but the overall strategy does not establish that all proposed investments have already received approval.
Key Insights
The South Australian plan combines underground mine development with additional processing capability. Its long-term production milestones depend on project studies, capital allocation and the successful sequencing of separate investments across the copper province.