Key Highlights
- Avira Resources completed 37 reverse circulation holes spanning 4,234 metres at Mt Cattlin after the September quarter ended.
- The first drilling Tranche returned seven metres grading 6.11 grams per tonne gold at Maori Queen.
- Geological review placed Sirdar among the priority prospects for the resumed drilling campaign, alongside first-pass work at Ellendale.
- Quarterly exploration expenditure reached AUD 462,000, while the company reduced its interest in the Swedish Puolalaki project to 49%.
Avira Resources (ASX:AVW), a mineral exploration company with projects in Western Australia and Sweden, reported progress across its gold and base metals portfolio on 26 October 2026. Its September quarter report detailed the initial results from Mt Cattlin and subsequent completion of the Reverse Circulation Drilling campaign, together with changes to its other project interests.
Mt Cattlin drilling programme and initial assays
The Mt Cattlin Gold Project lies approximately 550 kilometres southeast of Perth and four kilometres north of Ravensthorpe. Avira holds mineral rights within exploration licence E74/401, excluding pegmatite minerals. Its exploration programme includes the Maori Queen, Plantagenet, Sirdar and Ellendale prospects.
The initial tranche comprised 18 holes totalling 1,910 metres. Results from these holes were released during August 2026, covering Maori Queen and Plantagenet. At Maori Queen, hole RAGC116 intersected seven metres at 6.11 grams per tonne gold from 105 metres, including two metres at 15.1 grams per tonne from 107 metres. Other intervals in the same hole included two metres at 1.63 grams per tonne from 61 metres and two metres at 1.31 grams per tonne from 101 metres.
Hole RAGC108 recorded four metres at 3.86 grams per tonne from 23 metres, including one metre grading 13.75 grams per tonne. At Plantagenet, RAGC102 returned eight metres at 2.77 grams per tonne from 16 metres. The company reported gold mineralisation across a strike length of 650 metres at Maori Queen and the New Zealand Trend, with mineralisation remaining open at depth.
Sirdar and Ellendale enter the drilling schedule
Wet winter conditions temporarily interrupted drilling. The contractor returned to site towards the end of September, commencing initial reverse circulation work at Sirdar and Ellendale before testing extensions beneath Maori Queen along the broader New Zealand Trend.
Historical drilling at Sirdar included intervals of one metre at 131.24 grams per tonne gold and six metres at 50.07 grams per tonne. These results predate Avira's current programme and are distinct from its new assays. Historical Ellendale intersections included ten metres at 2.70 grams per tonne from 77 metres and 13 metres at 1.51 grams per tonne from 24 metres.
After quarter-end, the first phase concluded with 37 holes and 4,234 metres drilled. The contractor subsequently departed the site and samples were submitted for laboratory analysis. Avira intends to release additional assays progressively and refine targets for its approved second drilling phase. The company is targeting an initial mineral resource estimate in the first quarter of 2027, subject to the results and assessment work.
Tangadee tenure and Swedish project interests
The Tangadee project in the Ashburton region encompasses exploration ground near the faulted contact between the Edmund and Collier basins. Following a review of historical electromagnetic and magnetic datasets, Avira surrendered 75 blocks from licence E52/4411 that it considered lower priority. No substantial work was undertaken at Tangadee during the September quarter. Proposed work includes ground electromagnetic surveys and subsequent testing of selected anomalies.
In Sweden, Avira elected not to proceed with the third stage of its Puolalaki earn-in, reducing its interest to 49%. The parties are considering Options to advance the nickel, copper and gold project.
Quarterly expenditure and next milestones
Avira recorded exploration expenditure of AUD 462,000 and related-party payments of AUD 73,000 for directors' fees, Superannuation and administration or consulting services. Operating cash outflow totalled AUD 132,000, while investing cash outflow was AUD 460,000. Andrew van Bentum commenced as chief executive on 1 July 2026.
The next reported milestones at Mt Cattlin are the outstanding laboratory results and assessment of targets for the second phase of drilling. The resource estimate remains a stated target rather than a completed outcome.