Highlights
- BHP (ASX:BHP) presented a two-phase Copper South Australia expansion pathway during its November 2026 site tour.
- The first phase targets approximately 500,000 tonnes of copper annually by 2035, subject to development decisions.
- Carrapateena expansion includes a proposed block cave and additional concentrator capacity, with a potential decision in 2028.
- The second phase considers Ankata or Olympic Dam Deeps as alternative sources of additional production.
BHP (ASX:BHP) is a diversified Mining group with operations spanning iron ore, copper and other commodities. Its South Australian copper province includes Olympic Dam, Carrapateena and Prominent Hill. The November 2026 site tour outlined a staged approach to increasing underground mine output and expanding associated processing infrastructure over the next two decades.
Copper Output Targets and the FY26 Production Base
Copper South Australia produced 321,000 tonnes in FY26, up 2% year on year. The company has outlined a pathway to approximately 500,000 tonnes annually by 2035 and up to 650,000 tonnes by 2040. These future volumes are development objectives rather than committed production guidance. The FY27 production range for the province is 290,000–320,000 tonnes, illustrating the distinction between near-term operating expectations and longer-term expansion scenarios. Copper-equivalent production targets also incorporate the contribution of other metals and should not be confused with copper output alone.
Carrapateena Block Cave and Concentrator Expansion
The Carrapateena proposal involves a block cave approximately 450 metres below the existing sublevel cave. BHP has approved USD 366 million in pre-commitment funding for mine development and enabling works, while the broader expansion carries an indicative Capital range of USD 1.8–2.1 billion. A potential final Investment decision is scheduled for the first half of calendar 2028. First production is targeted for FY30, followed by a ramp-up period. A new concentrator would add five million tonnes of annual capacity to the existing seven-million-tonne facility. These plans remain subject to engineering and investment assessment.
Smelter Investment and Olympic Dam Processing
The proposed first stage of smelter and refinery expansion has indicative capital requirements of USD 3.2–4.1 billion, with a possible investment decision in the second half of 2027. A separate mine and concentrator development option has an indicative range of USD 4.1–5.4 billion and a potential 2029 decision. The estimates are expressed in real terms at 1 July 2026. The sequencing matters because higher mining volumes require corresponding processing capability. Water, power and other enabling infrastructure also form part of the broader development pathway.
Ankata and the Second Development Phase
Ankata, formerly Oak Dam, has a reported resource containing 8.8 million tonnes of copper, with an updated estimate expected in 2027. BHP is considering either Ankata or Olympic Dam Deeps for the second phase, with indicative capital of USD 4.5–5.8 billion and a possible investment decision in 2032. Resource estimates do not establish economically recoverable reserves. The eventual development configuration depends on further geological and engineering assessments, infrastructure requirements and capital allocation decisions. The production pathway therefore remains conditional rather than a fixed construction schedule.
Key Insights
The expansion strategy links underground mining, concentrator capacity and Downstream processing through separate investment decisions. Its ultimate production profile depends on project selection, technical studies, infrastructure delivery and the approval of substantial capital commitments.