Key highlights
- American Rare Earths (ASX:ARR) reported a first Probable Ore Reserve at Cowboy State Mine.
- The pre-feasibility study modelled a 26-year operation.
- The model estimated pre-production Capital of USD 840 million including contingency.
American Rare Earths (ASX:ARR) traded 9.62% lower at AUD 0.235 on 20 November 2026. The S&P/ASX 200 also traded lower during the session. The company, a rare earths project developer in Wyoming, reported a pre-feasibility study and maiden probable reserve for Cowboy State Mine on 19 November 2026.
A first reserve for part of Halleck Creek
American Rare Earths announced on 19 November 2026 that it had completed a pre-feasibility study and declared a maiden Probable Ore Reserve at Cowboy State Mine, the first development phase of its Halleck Creek project in Wyoming. The reserve is 116.4 million tonnes at 1,257 parts per million payable rare earth oxide. The mine schedule in the study is based entirely on Probable Ore Reserves derived from Indicated Mineral Resources. The study covers less than 5% of the total Halleck Creek resource. The wider resource and the reserve-based study therefore describe different scales and levels of development definition.
A 26-year schedule and preliminary capital estimates
The study evaluated Mining and processing 4.5 million tonnes per year for 26 years. It estimated average annual neodymium-praseodymium oxide output of approximately 2,500 tonnes. The after-tax net present value was approximately USD 1.3 billion at an 8% real discount rate, and the after-tax internal rate of return was 24%. Pre-production capital was estimated at about USD 840 million including contingency. The company described the estimates as targeting accuracy of plus or minus 25%, with 15% contingency on direct capital. These are modelled outcomes and costs at the pre-feasibility stage.
Recovery assumptions are important to the study
American Rare Earths reported recovery optimisation work with Novex. Its modelling indicated that a one percentage point increase in neodymium-praseodymium recovery could add about USD 50 million to net present value under the sensitivity assumptions. Recovery describes how much of the relevant material in the feed can be captured in processing and affects the modelled output. Metallurgical improvements would have to be demonstrated through further technical work. The company is also assessing yttrium as a possible future product, separate from the stated assumptions for the current neodymium-praseodymium production estimate. The study assumes neodymium-praseodymium oxide recovery of 58.2% and compares the effects of changes in recovery and product prices. Its sensitivity analysis identifies both variables as material to the modelled economics.
What a deeper study could change
The pre-feasibility work builds on an updated scoping study released on 30 September. The company said drilling to support resource-to-reserve conversion for the feasibility study had been completed. Updated estimates can change as the company refines engineering, metallurgy and cost assumptions. Financing and regulatory processes affect possible execution of the project. The forecast capital and modelled returns show the scope of the case being assessed and do not establish future results. Process recovery, product prices and capital requirements remain relevant comparisons as the company advances into the next study stage.
The study’s comparison with the earlier scoping case also put after-tax payback from first capital at 6.4 years, down from 6.9 years in the scoping case. At a 10% real discount rate the modelled after-tax value was USD 966 million, compared with USD 764 million in the September case.
Changes from the September scoping case
The September scoping case and the November pre-feasibility case both used throughput of 4.5 million tonnes a year and average annual neodymium-praseodymium output of about 2,500 tonnes. The capital estimate including contingency came down from USD 900 million to USD 840 million. Within that total, the contingency estimate moved to USD 114 million from USD 208 million as the company reported a tighter estimation range. The modelled net present value at the same 8% real discount rate rose from approximately USD 1.07 billion to USD 1.3 billion after tax. The revised study modelled construction from 2028 to 2030 and production from 2031. These schedules and figures reflect the proposed development case. Further engineering and financing work will be needed to establish whether a construction schedule and capital plan can be implemented as modelled.
A baseline for feasibility work
Cowboy State now has a reserve-based schedule and a modelled cost and production case. The next technical work can show how much the reserve basis, recovery assumptions and development costs change when the project is assessed in more detail.