Key highlights

  • Forrestania Resources (ASX:FRS) signed a long-term reagent Supply agreement for Edna May.
  • It awarded ore loading and crusher feed work to Campbell Gold Haulage.
  • The company created a Goldfields operations hub in Kalgoorlie.

On 20 November 2026, Forrestania Resources (ASX:FRS) traded at AUD 0.245, down 9.26% during the session. The S&P/ASX 200 benchmark also declined during trading. The company, a Western Australian gold mine developer, reported supply and logistics arrangements at Edna May and a new Goldfields hub on 20 November 2026.

Supply secured ahead of planned processing

Forrestania Resources announced three steps toward production readiness at its Edna May Gold Mine on 20 November 2026. It executed a long-term supply agreement with Australian Gold Reagents for sodium cyanide, a reagent used in gold recovery. The agreement secures an input for the plant. It reported about 60,000 tonnes of ore available for processing on the run-of-mine pad and identified December as its target for initial processing and a first gold pour. The timing remained a company plan. Having material available for processing and arranging supplies are milestones in preparing the operation.

Loading and plant feed awarded to the existing haulier

Campbell Gold Haulage received the ore loading and crusher feed contract, with equipment and personnel mobilisation underway. The contract supports ore handling and plant feed at Edna May and Lake Johnston. Campbell already held the road train contract, so the arrangements put the transport and loading work with the same contractor where material passes through the run-of-mine stockpiles. These contracts deal with handling and moving ore within the operating chain. The company has described mobilisation as underway. Processing and eventual gold output depend on later milestones at the plant. Forrestania also reported that ore inventories at Lake Johnston exceeded 180,000 tonnes. The new loading agreement therefore addresses ore handling at two sites, while the reagent agreement is specifically for Edna May.

The run-of-mine stockpiles provide a place to hold mined material before it is moved into the plant feed schedule. Ore on those pads is available for handling and processing, subject to site preparation and operating readiness.

A regional base for operations

Forrestania opened an office in Kalgoorlie to support its Goldfields workforce. The office is shared with Mega Resources and led by newly appointed General Manager Mining Darren Gaby. Forrestania cited his previous operating and project development roles in the region, including work on the Jaurdi Gold Project from construction through production. Establishing the regional office gives the company a location to coordinate staffing and site activity. Its other November announcements in the filing were a new corporate website and the Edna May supply and services arrangements. The office serves broader regional work alongside planning for Edna May.

What the two locations contribute to the start-up plan

The November update separates ore available at Edna May from a larger stockpile at Lake Johnston, where the company said inventories were continuing to build. Loading and crusher feed services are relevant to both properties. The gold recovery reagent agreement, by contrast, identifies Edna May as its specific supply destination. Forrestania described the two arrangements as supporting the transition from dry to wet commissioning at Edna May, when the operation progresses from equipment checks toward running with material and process inputs. The mine manager and Kalgoorlie office support the workforce across the region. The release therefore describes work at the processing site, ore handling across two locations and an organisational change that supports both. The scheduled first gold pour relates to Edna May and will depend on the progress of commissioning and processing rather than the amount of stockpile disclosed on its own.

What still has to line up before processing

Ore availability and contracts are preparatory measures. Starting the campaign depends on having transport and loading ready, securing a consistent feed to the plant and completing preparations for processing. The tonnage on the pad is the quantity reported as available, while actual plant throughput will depend on the schedule and operating performance. The release discloses neither recovered ounces nor campaign revenue. Those details depend on material being processed and on its grade, recovery and eventual sale. The identified service and supply arrangements address specific parts of the production chain as the company prepares for its first campaign.

The next milestones at Edna May

Initial processing and a first gold pour were targeted for December. Those are distinct from the signing of contracts. Subsequent operating results can show how much ore was treated and how the supply and handling arrangements supported the startup.