Highlights

  • Woodside Energy (ASX:WDS) reported Louisiana LNG 32% complete, with first LNG targeted for 2029.
  • The Trion project in Mexico was 71% complete, with first oil targeted for 2028.
  • The company is selling its 70% operated interest in Calypso, with completion targeted for the fourth quarter of 2026.
  • Woodside took over operatorship of the Gippsland Basin Assets on 1 July 2026.
  • New pipeline gas sales were agreed for Western Australia and the East Coast.

Woodside Energy Group (ASX:WDS) is advancing a portfolio of long-dated developments in the United States and Mexico while adjusting its asset mix elsewhere. Its third quarter 2026 report, released on 20 October, showed Louisiana LNG 32% complete and the Trion deepwater oil project 71% complete, alongside a series of divestments, operatorship changes and gas sales agreements.

Louisiana LNG

The Louisiana LNG project is on budget, with first LNG targeted for 2029. Train 1 was 41% complete, Train 2 was 27% and Train 3 was 22%. Stonepeak and Williams are named in the report as participants contributing cash to the project. Woodside (ASX:WDS) said discussions are continuing with high-quality counterparties on Equity and LNG offtake, and the report did not name a specific agreement. The project is the largest of the company's longer-dated commitments, and its timetable extends well beyond the current Scarborough start-up.

Trion and Exploration

Trion, in the Gulf of Mexico, was 71% complete and on budget. Fabrication of the floating production unit was 96% complete, and 10 of 24 wells had been drilled, with first oil targeted for 2028. In exploration, the Nasim-1X well in Egypt's Tiba licence, where Woodside holds a 40% non-operated interest, was spudded in August 2026 and drilling was ongoing. The company was awarded one US Gulf of America Lease and signed a non-binding memorandum of understanding with PEMEX to evaluate deepwater opportunities in the Gulf of Mexico.

Portfolio Changes and Gas Sales

Woodside (ASX:WDS) is selling its 70% operated interest in Calypso, with completion targeted for the fourth quarter of 2026, and expects an asset swap involving Wheatstone and Julimar-Brunello to complete in the same period, subject to regulatory approvals. It took over operatorship of the Gippsland Basin assets on 1 July 2026 and is assessing four proposed Bass Strait development wells, depending on technical reviews and the federal domestic gas reservation scheme. New pipeline gas sales of 12.9 petajoules to Western Australia for 2027–2029 and 18.4 petajoules to the East Coast for 2026–2028 were also agreed.

Beaumont New Ammonia

Beaumont New Ammonia had a process safety event that suspended operations for about 30 days, and third-quarter output was limited to 69% of nameplate capacity. The plant has restarted, and a strategic review is complete. Woodside (ASX:WDS) will begin a formal process to reduce its investment, with lower-carbon ammonia production targeted for 2027. The risks across the portfolio include construction schedules, regulatory approvals, partner arrangements and operating performance at newly acquired assets.

Key Insights

Woodside Energy (ASX:WDS) is balancing large development projects with portfolio adjustments. The company's disclosures show Louisiana LNG and Trion advancing to budget, while the ammonia plant and several asset transactions remain subject to reviews or approvals, so completion milestones and offtake or equity arrangements are the main items to follow.