Highlights

  • Santos (ASX:STO) reported record third-quarter 2026 production of 26.3 mmboe, up about 14% on the previous quarter.
  • Barossa reached steady production, with Darwin LNG operating at 98.5% reliability.
  • Pikka lifted its first oil cargo in August and ended the quarter at about 69,000 barrels a day (gross).
  • Full-year 2026 production guidance was narrowed to 99–102 mmboe from 99–105 mmboe.
  • About half of third-quarter free Cash Flow came from international operations in Papua New Guinea and Alaska.

Santos Limited (ASX:STO) released its third quarter 2026 report on 22 October, describing a record quarter as its two newest projects moved from construction towards steady operation. Production reached 26.3 million barrels of oil equivalent, up almost 14% on the second quarter and 23% on the same quarter a year earlier. The report also narrowed full-year guidance after temporary disruptions at the Pikka oil project in Alaska.

A Record Quarter

Year-to-date production reached 71.9 mmboe, about 10% above the prior corresponding period, and third-quarter sales volumes were 26.4 mmboe. Sales Revenue was about US$2.0 billion, up 49% on the second quarter, and free cash flow from operations was a record of about US$1.07 billion. Roughly half of third-quarter free cash flow came from Papua New Guinea and Alaska. Santos (ASX:STO) narrowed 2026 production guidance to 99–102 mmboe, from 99–105 mmboe.

Barossa and Pikka

At Barossa, the company said production reached steady levels during the quarter, with feed gas peaking at about 600 million standard cubic feet a day. Darwin LNG ran at 98.5% reliability, and ten LNG cargoes and two condensate cargoes were lifted. At Pikka, the first oil cargo was lifted in August and five cargoes were lifted in the quarter. Seawater injection began, and output briefly reached the minimum expected plateau rate before ending the quarter at about 69,000 barrels a day gross. A weather event at the seawater treatment plant, a pipeline shutdown after a road accident and a suspension of Import gas Supply all limited output. Santos plans to hold output near 70,000 barrels a day briefly before ramping towards 80,000.

Portfolio and Offtake Developments

Santos (ASX:STO) signed a binding agreement to acquire a further 3.3% of Papua LNG from TotalEnergies, which would take its interest to 21% after the State back-in. Completion depends on regulatory approvals, and a final Investment decision is planned for the fourth quarter of 2026. In Queensland, GLNG partners signed binding agreements under which Santos would take a 30% interest in the Greater Meridian coal seam gas project and become operator, subject to approvals. On the commercial side, key terms were agreed for a 10-year LNG supply arrangement with POSCO Steel, and a non-binding agreement covers about 1 million tonnes a year from the proposed Ksi Lisims LNG project in Canada.

What to Watch

The main variables for Santos (ASX:STO) are the pace at which Pikka reaches plateau, the reliability of Barossa through a full quarter, and the timing of regulatory approvals for Papua LNG and Greater Meridian. Moomba carbon capture and storage has stored more than 2.5 million tonnes of carbon dioxide equivalent since September 2024. Guidance remains subject to operating performance, weather and project timing.

Key Insights

Santos (ASX:STO) is moving from a construction phase to a production phase, with Barossa and Pikka now contributing to quarterly output. The company's disclosures show that the narrowed guidance reflects temporary Pikka constraints, so the Alaska ramp-up and pending approvals on Papua LNG and Greater Meridian are the key items to follow.