Highlights

  • Woodside Energy (ASX:WDS) reported third-quarter 2026 production of 46.2 MMboe, up 12% on the second quarter.
  • The Scarborough Energy Project was 99% complete and on budget, with first LNG targeted for the fourth quarter of 2026.
  • Operating revenue was US$4,281 million, up 2% on the previous quarter.
  • Full-year production guidance was narrowed to 174–181 MMboe from 174–185 MMboe.
  • A fully Franked Dividend of US$1,084 million was paid and a US$800 million bond was repaid in the quarter.

Woodside Energy Group (ASX:WDS) reported a recovery in third-quarter 2026 output after a period of planned maintenance, while its Scarborough Energy Project in Western Australia moved close to completion. The report, released on 20 October 2026, showed production of 46.2 million barrels of oil equivalent (503,000 barrels a day), up 12% on the previous quarter but 9% below the third quarter of 2025.

Production and Financial Position

Woodside said the quarterly increase followed completion of the Pluto LNG turnaround in the second quarter and the North West Shelf turnaround in the third. Year-to-date production was 132.7 MMboe. Operating Revenue of US$4,281 million was up 2% on the second quarter and 27% on the third quarter of 2025, and quarterly Capital Expenditure was US$722 million. At 30 September, Liquidity was about US$7.8 billion and net debt, including leases, was about US$8.9 billion. During the quarter Woodside (ASX:WDS) paid a fully franked dividend of US$1,084 million and repaid a US$800 million bond.

Scarborough and Pluto Train 2

The Scarborough Energy Project and Pluto Train 2 were each 99% complete and on budget at quarter-end. Gas from the Scarborough reservoir was introduced to the floating production unit and exported into the trunkline during the quarter. All mechanical runs of the Train 2 compressors were complete, and Scarborough gas reached the warm end of the train after quarter-end while cold-end work continued. Modifications to Pluto Train 1, which will also process Scarborough gas, were continuing. The company reiterated that the first LNG cargo is targeted for the fourth quarter of 2026, which Woodside (ASX:WDS) describes as on track and within the approved budget.

Sangomar and Guidance

At Sangomar offshore Senegal, average production was 94 thousand barrels a day on a 100% basis, or 73 thousand barrels a day net to Woodside, with reliability of 99.2%. The company attributed lower output to natural field decline and a reduced production-sharing entitlement after pre-final-investment-decision costs were recovered. Full-year production guidance was narrowed to 174–181 MMboe, reflecting lower volumes at Beaumont New Ammonia and the Okha floating production unit, as well as the timing of the first Scarborough cargo. Capital expenditure guidance of US$4.0–4.5 billion was unchanged.

Risks and Watch Points

Woodside (ASX:WDS) sells much of its LNG under oil-linked contracts, so revenue depends on how realised prices follow contract formulas and on commissioning performance. Items to follow include the date of the first Scarborough cargo, the ramp-up of Pluto Train 2, operating reliability across the North West Shelf, Pluto and Sangomar, and any further changes to full-year guidance.

Key Insights

Woodside Energy (ASX:WDS) has moved past a maintenance-affected period and is close to starting LNG production from Scarborough. The company's disclosures show a narrowed production range and unchanged capital guidance, so the date of the first cargo and the commissioning of Pluto Train 2 are the key milestones.