Key highlights

  • Capricorn Metals reported 31,218 ounces of gold production at Karlawinda in its report dated 29 October 2026, at an AISC of $2,005 per ounce.
  • Cash and gold on hand was $535.0 million, and the company reported record FY26 Underlying Profit before tax of $467.5 million.
  • Construction and commissioning of the Karlawinda Expansion Project were completed, targeting 6.5Mtpa throughput.
  • The Mt Gibson Gold Project received federal environmental approval, and the Ore Reserve estimate was updated to 195.7 million tonnes.

Capricorn Metals (ASX:CMM) released its Activities Report for the September 2026 quarter on 29 October 2026, covering production at the Karlawinda Gold Project, commissioning of the Karlawinda Expansion Project and approvals for the Mt Gibson Gold Project.

Karlawinda Operations

Karlawinda produced 31,218 ounces of gold in the quarter, compared with 30,437 ounces in the June quarter, at an All-In Sustaining Cost of $2,005 per ounce against $1,648. The company said the result and the commissioning of the expansion keep the project on track for FY27 guidance of 137,000 to 147,000 ounces at an AISC of $1,900 to $2,100 per ounce. Quarterly Cash Flow from operations was $113.1 million, mill throughput was 1.13 million tonnes and 4.4 million bank cubic metres of material were mined.

Cash, Sales and Dividends

Cash and gold on hand was $535.0 million, up from $507.0 million. Gold sales of 27,516 ounces at an average realised price of $6,115 per ounce generated $168.3 million, and a further 4,442 ounces on hand were valued at $26.8 million. Capricorn reported FY26 underlying profit before tax of $467.5 million, up 71%, declared a fully franked final Dividend of 5 cents per share and completed the Big Springs Project divestment for up to $26.0 million. FY26 dividends totalled 10 cents per share, or $45.7 million, and a tax payment of $90 million to $100 million is expected in the second quarter.

Expansion and Mt Gibson

The Karlawinda Expansion Project was completed on schedule and within budget, and the new circuits reached the targeted steady-state throughput of 6.5Mtpa, initially processing low-grade ore. The company expects production of about 150,000 ounces a year with a mine life of more than 10 years on existing reserves. At Mt Gibson, detailed engineering is complete, major contracts are awarded subject to approvals and the federal Minister's delegate approved the project under the EPBC Act. A Western Australian Environmental Review Document has been submitted.

Resources and Reserves

The group Ore Reserve estimate was updated to 195.7 million tonnes at 0.8g/t for 5.24 million ounces, including 76.4 million tonnes at Karlawinda for 1.57 million ounces. The Mt Gibson open pit reserve is 114.3 million tonnes at 0.9g/t for 3.31 million ounces, and a maiden underground reserve is 5.0 million tonnes at 2.3g/t for 365,000 ounces. An updated pre-feasibility study describes a 19.25-year, 3.51 million ounce project.