Key Highlights

  • Ramelius Resources (ASX:RMS) maintained FY27 gold production guidance of 205,000 to 225,000 ounces.
  • Cash and gold increased to A$768 million at the end of September.
  • The company integrated a new crusher and cyclone tower at Mt Magnet during an October shutdown.
  • The updated four-year outlook adds 75,000 ounces of expected gold production across the period.

Ramelius Resources (ASX:RMS) maintained its FY27 production guidance in the September 2026 Quarterly Report and detailed progress on the Mt Magnet plant expansion. The update followed a higher four-year production outlook, which the company attributed to exploration results.

Quarterly cash and plant work

Ramelius generated A$186 million in Operating Cash Flow and A$62 million in underlying free cash flow for the quarter. At the end of September it held A$768 million in cash and gold, up from A$650 million at June. Mt Magnet milled 526,000 tonnes during the quarter. The company subsequently integrated new equipment into the existing circuit and had awarded a contract for a second circuit designed to process three million tonnes a year.

FY27 guidance and the longer-term target

Management maintained FY27 guidance of 205,000 to 225,000 ounces at an All-In Sustaining Cost of A$2,150 to A$2,350 per ounce. The four-year plan targets more than 600,000 ounces in FY30. Delivering that plan depends on the timing of expansion work and bringing higher-grade ore into the Mining schedule at Dalgaranga and Cue.

What Company Does

Ramelius Resources produces gold in Western Australia and is expanding its Mt Magnet plant as it develops feed sources at Dalgaranga and Cue. Mt Magnet provides processing capacity for ore from the wider operating plan. The group is both modifying the existing circuit and adding a second one, while exploration and mine development help determine where future feed will come from.

Risks to Weigh

The longer-term production outlook depends on expanding the mill and bringing higher-grade ore into the schedule. Delays in either workstream could lower near-term output or raise unit costs. Integrating new equipment can interrupt plant availability or take longer than planned. If higher-grade ore becomes available later than expected, extra plant capacity may initially do less to improve group production or costs.

What to Watch Ahead

Watch progress on the second processing circuit, the timing of ore delivery from Dalgaranga and Cue and quarterly performance against FY27 cost and production guidance. Look for milling volumes after the upgrades and updates on the order in which ore sources will enter the plan. The effect of expansion spending can also be assessed against underlying free cash flow.