Key Highlights

  • Eclipse Metals Limited (ASX:EPM) reported on its 2026 operating activities, financial position and project developments. Its recent disclosures address Ivigtût mineral resources, Grønnedal drilling and technical evaluation in Greenland.
  • In July 2026, Eclipse released a maiden inferred mineral resource at the historic Ivigtût mine of 4.
  • Field activities included mapping and rock-chip sampling at Grønnedal during August, with 54 samples sent for laboratory analysis.
  • the company reported an Ivigtût Inferred Mineral Resource of 4.87 Mt grading 188 ppm HfO2.
  • It contracted a 17-hole, 2,355-metre diamond drilling programme at Grønnedal and held AUD 2.9 million in closing cash.

Eclipse Metals Limited (ASX:EPM) explores for critical minerals in Greenland and maintains uranium interests in Australia. Its shares were quoted at AUD 0.011, down 8.33%, on 4 November 2026. Exploration work at Ivigtût and Grønnedal has involved mineral resource reporting, sampling, technical studies and preparation for further drilling.

In the quarterly activities report dated 29 October 2026, the company detailed a maiden hafnium-led Inferred Mineral Resource at Ivigtût and plans for additional diamond drilling at Grønnedal. It also reported a return to full ownership of the Liverpool Uranium Project and cash of AUD 2.9 million at quarter-end.

Projects and Operating Milestones

In July 2026, Eclipse released a maiden inferred mineral resource at the historic Ivigtût mine of 4.87 million tonnes grading 188 parts per million HfO2, 61 ppm Ga2O3, 147 ppm Y2O3 and 3,380 ppm zirconium at the stated cut-off. The resource covers several critical mineral elements in addition to the historical cryolite setting. At the nearby Grønnedal rare-earth deposit, the group reported a total JORC mineral resource estimate of 208 million tonnes grading 7,239 ppm total rare-earth oxides, consisting of approximately 6 million tonnes indicated and 202 million tonnes inferred. Resource categories do not represent an approved mine or proven economic extraction.

Reported Financial and Corporate Figures

Field activities included mapping and rock-chip sampling at Grønnedal during August, with 54 samples sent for laboratory analysis. Mineralogical work across four composite samples indicated that 87.5%–94.3% of contained neodymium and praseodymium occurred in identified rare-earth-bearing mineral groups. Eclipse also entered an agreement for a 17-hole, 2,355-metre drilling program at Grønnedal to test selected portions of the resource and potential extensions. Two diamond rigs commenced operations following the quarter end. Further testing is required to establish recoveries and the performance of any selected processing method.

Technical Programme and Outstanding Work

In the Northern Territory, Eclipse regained full ownership of its Liverpool Uranium Project after the previous option and earn-in arrangement ended. Traditional Owner consent was received for a defined exploration program at licence EL 27584 covering airborne surveying, access assessment, sampling and up to 12 helicopter-supported diamond holes. the company began reviewing potential funding and partnering structures for its broader portfolio but did not report a binding financing transaction during the September quarter. This separates current field work and approvals from possible future commercial arrangements.

The Grønnedal drilling program was designed partly to test selected areas of the inferred resource for possible conversion to a higher-confidence classification. Geological mapping and sampling were complementary activities, not substitutes for drilling and metallurgical tests. the company stated that mineral separation and processing Options remained under technical review. Its Liverpool work program was also defined by separate exploration permissions and Traditional Owner engagement. Eclipse had received no completed binding strategic funding transaction by the end of the reporting quarter. Exploration results, laboratory mineralogy and discussions with prospective participants therefore remained separate categories of activity within its wider 2026 portfolio.

Key Insights

the company reported a combination of completed 2026 activity and work scheduled for later periods. Its disclosed figures distinguish reported operating results or cash balances from targets, estimates and proposed arrangements. The principal developments covered here relate to greenland rare earths drilling and ivigtut critical minerals resource. Future programs remain subject to the specific approvals, financing, commercial terms or technical results identified in the company’s disclosures. The share-price Quotation presented above is a historical reference and is not described as a verified live quote for 4 November 2026.