Key Highlights
- HAZER Group (ASX:HZR) traded 7.69% lower at $0.24, Kinetiko Energy (ASX:KKO) 7.14% lower at $0.026 and Delorean Corporation (ASX:DEL) 6.45% lower at $0.058.
- Recent updates covered a quarterly report, a funding update and financial close on a bioenergy facility.
- The updates were released between 19 October and 9 November 2026.
Three energy companies were among the ASX decliners during the Trading session on 27 November 2026. HAZER Group Limited (ASX:HZR) shares were 7.69% lower at $0.24, Kinetiko Energy Ltd (ASX:KKO) shares were down 7.14% at $0.026 and Delorean Corporation Limited (ASX:DEL) shares had fallen 6.45% to $0.058, while the S&P/ASX 200 index was at 8,795.50, up 0.36% or 31.70 points. Separately, each company has released news in recent weeks, covering hydrogen technology, South African gas and a bioenergy project. Here is a closer look at each update.
HAZER Group (ASX:HZR)
Hazer released its quarterly activities and cashflow report for the quarter ended 30 September 2026 on 19 October 2026. The company said it is building on a commercial-scale Process Design Package with KBR, reported a paid study with a Japanese energy Utility assessing hydrogen facilities of up to 300,000 tonnes per annum, and said Capital intensity has improved by about 12%.
It said the Whyalla steelworks sale process continues, with M Resources one of two final bidders and a decision expected as early as the end of 2026. The company reported a funding position of $12.9 million.
Kinetiko Energy (ASX:KKO)
Kinetiko released a funding update on 28 October 2026 on its $5.4 million Placement of 180,000,000 shares at $0.03. A further $400,000 was received, and the final $3.5 million, including a $3.0 million commitment from major Shareholder Talent 10 Holdings, was to be put to shareholders at the 27 November 2026 AGM.
Together with cash of $1.127 million and the balance of the Mulilo co-operation fee, the company reported pro forma funding of about $6.0 million for Phase 1 at Brakfontein, permitting and Cluster 2 drilling in early 2027, with first commercial gas targeted for late 2027.
Delorean Corporation (ASX:DEL)
Delorean released an announcement on 9 November 2026 confirming financial close on the $62.1 million NSW1 Horsley Park Bioenergy Facility. The 25-year renewable gas Supply agreement with Building Products Pty Limited, the Lease with The Austral Brick Co and $30.5 million of grants are now active.
Funding includes a $20.0 million Westpac facility, $20.0 million NSW Government and $10.5 million ARENA grants, and a $1.4 million private placement. Construction is expected to start on site in early 2027.




_11_26_2026_09_15_12_447191.jpg)

Please wait processing your request...