Key Highlights

  • Woodside (ASX:WDS) reaffirmed at its 5 November Capital Markets Day that Scarborough’s first LNG cargo remained on track for Q4 2026.
  • The Scarborough and Pluto Train 2 projects were 99% complete at 30 September, excluding work to modify the existing Pluto Train 1.
  • During the September quarter, Woodside introduced offshore gas into the floating production unit and sent it into the trunkline.
  • Woodside gives the project a gross LNG capacity of 8 million tonnes a year, with domestic gas capacity of up to 225 terajoules a day.

Woodside (ASX:WDS) produces and markets liquefied natural gas, pipeline gas and oil. For its Scarborough project in Western Australia, the company is targeting a first LNG cargo in the final quarter of 2026. Woodside reiterated the timing in November, after its October Quarterly Report detailed the sequence of offshore and onshore commissioning work.

First cargo is targeted for the final quarter of 2026

The 5 November Capital Markets Day presentation kept the first shipment within the October-to-December window. Woodside did not specify a loading date in that update. Its September quarterly report, released on 21 October, placed the Scarborough and Pluto Train 2 projects at 99% complete and on budget, with the figure excluding changes to Pluto Train 1. Woodside’s project information subsequently described completion as above 99% on the same basis.

The percentage refers to work across the development, while the first cargo depends on the offshore and onshore facilities working together. The quarterly report recorded commissioning and start-up of the floating production unit and subsea system. Woodside introduced gas from the reservoir into the floating unit and sent it into the trunkline to pressurise it. The company said the results of well clean-up were in line with its expectations for the wells and reservoir.

Pluto Train 2 must move from gas treatment to liquefaction

Woodside completed mechanical runs of the Pluto Train 2 compressors. After the September quarter ended, Scarborough gas entered the train’s gas pretreatment section, where it is prepared for processing. Woodside also reported that work was progressing at the cold end of the train. That is where the Facility cools the gas into liquid form before it can be shipped.

The existing Pluto Train 1 is also being modified so it can process Scarborough gas. Woodside reported that the final module had reached the site and that work had shifted to connecting and integrating it. The overall project brings offshore production and the expanded Karratha processing facilities together along an approximately 430-kilometre pipeline. The Scarborough field lies in the Carnarvon Basin, about 375 kilometres off Western Australia’s Pilbara coast.

What the shipment adds to Woodside’s LNG portfolio

A first cargo would mark the point at which Scarborough begins supplying LNG for shipment from Pluto. Woodside puts gross LNG capacity at 8 million tonnes a year. That figure describes the project at full capacity and does not specify how quickly production will reach that level after start-up. The development also provides for up to 225 terajoules a day of domestic gas capacity.

The gross capacity covers the whole project. As at 30 September, Woodside held a 74.9% participating interest in Scarborough and 51% in Pluto Train 2. The company narrowed its full-year 2026 group production guidance from 174–185 million barrels of oil equivalent to 174–181 million. It cited a narrower window for the first Scarborough cargo among several factors behind that revision.

Key Insights

The first shipment will mark the start of LNG exports from Scarborough after offshore gas reached Pluto Train 2 for commissioning. Woodside’s Q4 target gives a window for the first cargo, while the project’s annual capacity describes a later stage of operations.