Key Highlights
- Production was 46.2 MMboe in the quarter, 12 per cent higher than the June quarter.
- Operating revenue was US$4,281 million, up 2 per cent on the June quarter.
- Scarborough is 99 per cent complete and on budget, with first LNG targeted for the December quarter.
- Full-year production guidance was narrowed to 174 to 181 MMboe.
Woodside Energy Group Ltd (ASX:WDS) reported third-quarter production up 12 per cent, with Scarborough nearing completion. What did Woodside Energy's third-quarter report show about a company between two big transitions, finishing Scarborough in Western Australia and building Louisiana LNG in the United States? The report for the quarter to 30 September 2026, published around 21 October, showed production of 46.2 million barrels of oil equivalent, Operating Revenue of US$4,281 million, Scarborough at 99 per cent complete and a first LNG cargo still targeted for the fourth quarter of 2026. It also showed a narrower production guidance range and several portfolio moves.
Production and revenue
Woodside produced 46.2 million barrels of oil equivalent (MMboe) in the quarter, or 503 thousand barrels a day. That was 12 per cent higher than the 41.3 MMboe of the June quarter, helped by the completion of maintenance, but 9 per cent below the 50.8 MMboe of the third quarter of 2025. Year-to-date production was 132.7 MMboe, 11 per cent lower than the same period a year earlier. Sales volumes in the quarter were higher than production at 51.1 MMboe.
Operating revenue was US$4,281 million, up 2 per cent from the June quarter and 27 per cent from a year earlier. Year-to-date revenue was US$11,727 million, up 18 per cent. The average realised price was US$84 per barrel of oil equivalent, roughly flat on the previous quarter's US$85 and 40 per cent above US$60 a year earlier. Realised prices for LNG produced rose to US$84 per Barrel of Oil Equivalent from US$66 in the second quarter, which the company attributed to price lags, portfolio optimisation and more encouraging gas hub pricing, along with Pluto LNG returning from maintenance. Operational reliability exceeded 99 per cent at Pluto LNG, the North West Shelf and Sangomar.
The picture is mixed: lower volumes than a year ago, but much more encouraging prices. Revenue growth therefore comes from price rather than output, which is a different thing from a sustained improvement in the underlying Business and leaves Earnings exposed to Commodity markets.
Guidance
Woodside narrowed 2026 production guidance to 174 to 181 MMboe from 174 to 185 MMboe, citing lower volumes from the Beaumont New Ammonia plant and reduced output from the Okha floating production vessel. Capital Expenditure guidance of US$4.0 billion to US$4.5 billion, and production-cost and other cost guidance, were unchanged. Capital expenditure in the quarter was US$722 million, and year-to-date capital expenditure and acquisitions were US$2,829 million, including a US$470 million payment for Beaumont New Ammonia.
The balance sheet
Net Debt including leases was about US$8.9 billion and Liquidity about US$7.8 billion. During the quarter Woodside paid a fully Franked Dividend of US$1,084 million. The company is funding a large build programme while still paying dividends, which is why the net debt trend and the timing of first Scarborough cash flows matter to anyone following it. The report does not break down how much of the net debt change came from the dividend versus capital spending, so no judgement is made here.
Scarborough, Trion and Louisiana LNG
Scarborough is the nearest catalyst. The project is 99 per cent complete and on budget, and management says it remains on track for first LNG cargo this year, with the target set in the fourth quarter of 2026. The timing is a company target, so slippage is possible. Chief executive Liz Westcott said increased quarterly revenue reflected higher production and encouraging realised prices.
Trion, an offshore Mexican oil development, is 71 per cent complete and on budget, with first oil targeted for 2028. Louisiana LNG, the largest growth project, is 32 per cent complete and on budget overall, with Train 1 at 41 per cent. First LNG is targeted for 2029. These projects shift the portfolio toward US and Mexican Assets a strategy that adds Diversification but also construction and cost-inflation risk over a multi-year build.
Portfolio changes and safety
Woodside agreed to sell its 70 per cent operated interest in the Calypso project to bp, with completion targeted for the fourth quarter of 2026. It also said it will begin a formal process to reduce its Investment in Beaumont New Ammonia after a strategic review. That asset has been a softer spot: it contributed to the lower production guidance, and the report recorded a Tier 1 process safety event there that suspended operations for about 30 days. Woodside recorded three process safety events in the quarter in total.
Selling Calypso and reducing exposure to ammonia would simplify the portfolio and focus capital on LNG and the major projects. The sale price and the terms of any Beaumont exit are not in the summary used for this article, so their financial effect cannot be assessed.
Sector and competitive position
Woodside competes with global LNG sellers, including US exporters and Middle East producers, many of them expanding capacity. Its edge is in established Australian infrastructure and long-term customers. The risk is that new Supply could weigh on prices later in the decade, around when Scarborough and Louisiana LNG would be producing at scale.
Risks and upcoming dates
The primary risks are commodity prices, project delivery, and safety performance. Gas and oil prices drive revenue directly, and the encouraging realised prices of recent quarters may not persist. Delivery risk includes Scarborough start-up, where the final one per cent of a project can be the most difficult, and the cost trajectory of Louisiana LNG. Operational risks include the asset reliability and process safety events already recorded. Higher debt and leases could magnify any shortfall.
Dates to note are straightforward. Woodside has scheduled Capital Markets Days on 5 November 2026 in Australia and 12 November 2026 in the United States, where it may update long-term plans, and its fourth-quarter report is due on 28 January 2027.