Highlights

  • Delorean Corporation (ASX:DEL) confirmed financial close on its NSW1 project.
  • The Horsley Park bioenergy Facility carries an AUD 62.1 million project cost.
  • Government grants totalling AUD 30.5 million form part of the funding structure.
  • The September report placed SA1 construction progress at approximately 90%.

Delorean Corporation Limited (ASX:DEL) develops, constructs and operates bioenergy infrastructure that converts organic waste into renewable gas, alongside related engineering services. Its stock closed at AUD 0.086 on 12 November 2026. In a November announcement, the company confirmed financial close for its NSW1 Horsley Park facility, allowing procurement to proceed before planned site construction in 2027. Delorean is also progressing its SA1 Salisbury project, with future Operating Revenue dependent on completing commissioning and moving facilities into commercial operation.

Bioenergy Operations and Project Portfolio

Delorean Corporation (ASX:DEL) combines engineering and project development with a model under which it intends to own and operate selected renewable gas infrastructure. The company’s facilities process separated organic waste to produce biomethane, and some projects also involve other renewable-energy or waste-management outputs. NSW1 at Horsley Park in New South Wales and SA1 at Salisbury in South Australia are distinct Assets at different development stages. Delorean also provides contracted engineering, operations and maintenance services, including work associated with an established Victorian bioenergy facility.

NSW1 Funding and Construction Programme

Delorean Corporation (ASX:DEL) announced on 9 November 2026 that financial close had been achieved for the AUD 62.1 million NSW1 development. The stated funding components included an AUD 20 million New South Wales government grant, AUD 10.5 million from the Australian Renewable Energy Agency, a AUD 20 million Westpac facility, previously funded project Capital costs and other funding sources. The company also disclosed private-placement commitments. Financial close activated its 25-year gas Supply and site-lease agreements connected with the project. Procurement was scheduled to start in November, with site construction expected in the first quarter of 2027; these remain future activities.

Production Design, SA1 and Financial Results

NSW1 is designed to process approximately 120,000 tonnes of organic waste annually, with approvals extending to 150,000 tonnes. Delorean Corporation (ASX:DEL) indicated approximately 253,000 gigajoules of renewable gas production per year as a project figure. The gas is intended for direct use in nearby brick Manufacturing and the announced assumptions indicate a reduction in the facility’s natural-gas use. Separately, SA1 was around 90% constructed at the September quarter-end, with commissioning and first gas expected in FY2027. FY2026 accounts recorded revenue of approximately AUD 9.34 million, EBITDA of about AUD 0.98 million and a net loss after tax of approximately AUD 0.12 million. These historical figures do not include a full year of commercial output from the new owned facilities.

Funding, Commissioning and Delivery Risks

Delorean Corporation (ASX:DEL) reported September-quarter customer receipts of approximately AUD 0.8 million and a closing cash balance of AUD 2.5 million, excluding specifically identified subsequent receipts. Project execution still involves procurement, construction costs, commissioning, feedstock availability and compliance with relevant operating approvals. NSW1’s grants and financing arrangements have conditions and project purposes, while commercial revenues will depend on facilities operating as intended. The next relevant disclosures include SA1’s first waste acceptance, renewable gas delivery, NSW1 procurement progress and subsequent financial reporting on the company’s construction and operating activities.

Key Insights

Financial close is a completed funding milestone for NSW1, not the completion of the facility itself. Delorean’s 2026 reporting also documented substantial progress at SA1, while its financial statements reflected a Business still developing owned infrastructure. Upcoming milestones will show how the announced funding, construction programme and commissioning work translate into operating capacity.