Key highlights

  • NuEnergy Gas (ASX:NGY) began major construction work at Tanjung Enim during August.
  • The early production facilities were about 48% complete at September end.
  • NuEnergy targeted first gas sales for Q1 calendar 2027, subject to completion of key facilities.

NuEnergy Gas (ASX:NGY) was quoted at AUD 0.021, 5.00% higher in the 20 November 2026 session as of 11:52 a.m. AEDT. The S&P/ASX 200 fell during the broader session. The Indonesian coal seam gas developer reported construction progress and the first gas sales target at Tanjung Enim on 28 October 2026.

Tanjung Enim construction advances

NuEnergy Gas reported September-quarter activities on 28 October 2026. The company said major construction for the Tanjung Enim development in South Sumatra started in August. Its early production facilities were approximately 48% complete at 30 September, with civil and piping work under way and statutory inspections still in progress. Work was also advancing at the compressed Natural Gas mother station being developed by offtake partner Perusahaan Gas Negara. The company reported that the station had reached about 23% completion by the end of the quarter. The two facilities are both part of the arrangement for the first gas sales.

The early sales initiative and full development

The early gas sales initiative is designed to deliver one million standard cubic feet per day. It sits within the first approved development plan, which envisages a total of 25 million standard cubic feet per day including the initial phase. The first development plan covers 33 square kilometres within the 249.1-square-kilometre production sharing contract area. NuEnergy holds a 45% participating interest in the contract, which is operated through its Dart Energy subsidiary. The company described the first plan as work to be carried out by NuEnergy singly and exclusively under the arrangements applicable to that development. Associated permits are required.

Gas sales agreement and government designation

The offtake partner has executed a gas sales and purchase agreement with a contract Volume of 5.59 billion cubic feet of coal bed methane from the early initiative wells. Indonesia also recognised Tanjung Enim as a National Strategic Project in September. NuEnergy expects the designation to facilitate coordination with government bodies involved in development. Work had started on securing access to land for the full development. The company also completed a Placement of around 80.2 million ordinary shares at AUD 0.038, raising approximately AUD 3.05 million to support commercialisation work and advance other project activity.

Coal bed methane requires connected infrastructure

Coal bed methane projects link well operations with production facilities and arrangements for handling and delivering gas. During the quarter, NuEnergy continued dewatering, flaring and optimisation activities at the four early initiative wells to evaluate reservoir behaviour. The company owns the early production facilities and its offtake partner is constructing the mother station. These two construction programs will need to align with work at the wells for sales to start. The larger development has its own land and infrastructure requirements, even as early facilities provide a basis for the first stage of operations.

First sales depend on Facility readiness

The company’s target for first sales depends on completing the early production facilities and the mother station, along with required commissioning. The September percentages reflect progress at that date. They indicate how much of each construction package the company described as complete, with remaining activities at both sites. A gas sales contract establishes contracted terms and volume. Delivery depends on operating facilities and progress at the wells. The separate process of securing land access will be relevant to the wider development beyond the earliest production phase, alongside any approvals needed for that work.

Commissioning and the next stage of development

NuEnergy targeted the first quarter of calendar 2027 for first commercial gas under the early initiative. Further milestones include completing both facility packages, commissioning the relevant equipment and continuing well optimisation. The programme for full development separately depends on how the company advances land access and infrastructure. NuEnergy also intends to use part of the funds raised in September to advance its other production sharing contract areas toward development plan status. The first sales target in the latest Quarterly Report applies specifically to the early operation at Tanjung Enim.

Tanjung Enim at quarter end

Both initial facility packages were under construction at 30 September. Their completion and commissioning are central to the planned first gas sales in early 2027.