Key Highlights
- Tlou Energy (ASX:TOU) recorded significant coal fines influxes at its Lesedi wells during production testing.
- Lesedi 6 was temporarily shut down, while monitoring continued at Lesedi 4.
- The Kala Data Centre continued at proof-of-concept scale using electricity from Lesedi.
- Cash was about A$57,000 at 30 September 2026, with A$2.87 million of a A$10 million Loan Facility undrawn.
Tlou Energy Limited (ASX:TOU) reported on production testing, power generation and funding in its quarterly activities report for the period ended 30 September 2026, released on 30 October 2026. The Botswana-focused gas-to-power company said production testing and dewatering continued at the Lesedi Project, where it encountered recurring coal fines influxes, and that the Kala Data Centre remained operational at proof-of-concept scale.
Lesedi Wells and Production Testing
Production testing, dewatering and well-performance monitoring continued at Lesedi 4 and Lesedi 6. Tlou said operations encountered several challenges, including significant and recurring coal fines influxes. After persistent coal influxes and pump inefficiencies, the company made a decision to temporarily shut down Lesedi 6. Monitoring and data collection continued at Lesedi 4 to support assessment of well performance and potential gas Supply for future expansion of the data centre. Development planning is not assuming an increase in available gas supply.
Tlou describes the Lesedi Project as its most advanced project. It integrates gas production from wells, gas gathering infrastructure and on-site power generation, which together form the basis of converting locally produced coal bed methane into electricity.
Kala Data Centre and Power Generation
Electricity generated at Lesedi continued to supply the Kala Data Centre at proof-of-concept scale. Planning focused on reviewing the gas-to-power process, finding operational improvements and assessing the power and infrastructure needed to expand. A hybrid gas and solar strategy remains under review, with Options for an initial 5 MW solar development. The company said the proposed solar integration has no binding agreement and is subject to funding and approvals.
Substation and Grid Connection
The Lesedi substation is about 90% complete, with the remaining construction deferred pending funding availability. The substation is intended to link on-site generation with grid-based electricity sales and to accommodate both gas-fired and solar generation.
Funding and Cash Flow
Tlou's Shareholder loan facility remains at A$10 million, of which A$7.13 million had been drawn at quarter end, leaving about A$2.87 million available. Cash at 30 September 2026 was about A$57,000 (unaudited). The quarter's net operating Cash Flow was an outflow of A$201k, investing cash flow was an outflow of A$237k and financing cash flow was A$370k, with available funding of A$2.93 million. Related party payments were A$45,000 for directors' salaries and fees. The company said it remains reliant on securing further funding for material development activities.
Any expansion remains subject to demonstrating sustained gas flow, reliable power generation, further funding and approvals. Well performance data from Lesedi 4 and discussions with potential financiers are the main items to follow.
In summary, the quarter combined continued testing and a proof-of-concept data centre with well challenges and a reported cash balance of about A$57,000.