Key Highlights

  • Saturn Metals said its environmental approval application for Apollo Hill will undergo a four-week public review in Western Australia.
  • The company estimates the public review and subsequent regulatory assessment could add about three months to the project development timetable.
  • Saturn moved its target for a final Investment decision from late 2027 to early 2028.
  • The definitive feasibility study is now targeted for early 2027 while the company evaluates additional engineering work identified during the study review.

Saturn Metals (ASX:STN) has revised the development timetable for its Apollo Hill Gold Project in Western Australia following advice from the state’s Environmental Protection Authority. The agency advised that the project’s environmental approval application will be subject to a four-week public review. Saturn has also moved the planned release of its definitive feasibility study to early 2027.

Public review and assessment at Apollo Hill

The review provides a four-week period for public comment on the application. Saturn expects the Environmental Protection Authority to assess the project after comments close. The company said it has commissioned or completed supplementary work it expects may be needed, while allowing for the possibility of further information requests.

The company estimates that the review and subsequent assessment together could add approximately three months to the project development timetable. Saturn has shifted the planned final investment decision from late 2027 into early 2028. It said it would provide permitting updates when appropriate. Its November announcement specified the duration of public review without giving opening or closing dates or setting a deadline for the ensuing assessment.

Feasibility work continues alongside permitting

Saturn has continued advancing the definitive feasibility study while the environmental process proceeds. The study has undergone financial model reviews, benchmarking and independent engineering peer reviews as part of the company’s validation work. Those reviews identified areas Saturn wants to examine further before publishing the study.

The company had targeted December 2026 for release. It is now allowing time for additional engineering and plans to incorporate the findings into the completed study. Managing director Ian Bamborough said the company intends to integrate the additional work with its project execution planning.

Saturn expects the engineering work to fit within the revised overall schedule. It attributed the movement in the final investment decision target to the regulatory timetable and identified the further engineering as the reason for the later feasibility study release.

Financing, construction and first gold targets

Saturn’s indicative development chart lists financing and procurement alongside regulatory approvals. It places construction and commissioning in the period after those workstreams and targets first gold in early 2029. The company explicitly makes that timetable subject to change and conditions operations on permitting, approvals, funding and an investment decision.

The chart records a resource update of 2.83 million ounces for the feasibility work and the grant of the Apollo Hill Mining lease. A reserve update is listed alongside the study, with both shown as in progress. Environmental assessment remains in progress in the company’s revised schedule. The November update sets out the expected order of the work and gives no new estimate of project Capital requirements.

The next milestones for Apollo Hill

The feasibility study is the next publication Saturn has given a target window, with disclosure planned for early 2027. The company’s schedule then places the final investment decision in early 2028, after allowing for further environmental assessment. The indicative first gold target follows in early 2029, subject to the approvals, funding and decision requirements shown in the chart.