Key Highlights

  • Niobium confirmed as hosted in pyrochlore, the same mineral mined at the world's major niobium operations
  • Zircon identified as potential by-product at 1.29% of the composite, more than twice the abundance of pyrochlore
  • 76-94% of pyrochlore liberates at a conventional crush below 212 microns
  • Rare earths report alongside niobium with the fines fraction grading 0.56% Nb2O5 and 2,951 ppm TREO

Chilwa Minerals Limited (ASX:CHW, Nasdaq:CHWM) has reported results from the first mineralogical characterisation of niobium-rare earth mineralisation from the Nakombe target within the Lake Chilwa licence in Southern Malawi.

Niobium Host Mineral Confirmed

QEMSCAN mineralogy identified pyrochlore (0.55% by mass) as the dominant niobium mineral, with minor columbite-Fe (0.06%). Pyrochlore is the same mineral mined at the world's major niobium operations, which the company considers a positive indicator for future processing pathway development. Below approximately 212 microns, 76-94% of pyrochlore occurs in liberated and high-grade middling particles, providing a clear starting point for concentration testwork.

Zircon By-Product Potential

Zircon was identified at 1.29% of the composite, more than twice the abundance of pyrochlore, with a calculated 0.95% ZrO2. Zircon liberates at a similar grind size, with 95-99% in zircon-dominant particles below 212 microns. Zirconium has not previously been part of the company's routine assay suite.

Rare Earths and Host Rock

Niobium and rare earths upgrade together into the fines, with the sub-45 micron fraction grading 0.56% Nb2O5 and 2,951 ppm TREO (1.7x and 1.8x the calculated head grade respectively). The host rock is relatively simple, with feldspar, mica, and quartz making up 93% of the composite, and low iron oxide, sulphide, and carbonate content. Thorium and uranium levels are low at 28 ppm ThO2 and 67 ppm U3O8.

The composite's calculated head grade of 0.33% Nb2O5 and 1,668 ppm TREO falls within the porphyry domain ranges of the Nakombe South Exploration Target. Three further domain composites are under analysis, and results will feed into a maiden Mineral Resource Estimate provisionally scheduled for the second half of 2027.