Highlights

  • Pivotal Metals (ASX:PVT) released a maiden scoping study for its 100%-owned Horden Lake project in Quebec.
  • The base case shows a post-tax NPV7 of A$920 million, an IRR of 49% and payback of 1.3 years.
  • Net pre-production Capital is A$411 million, including contingency of A$75 million.
  • The study models a 3.5Mtpa open pit with an initial 10-year life and All-In Sustaining Cost of US$1.00 per pound after credits.
  • The resource is 52.4Mt at 1.05% copper equivalent for 549,000 tonnes of copper equivalent.

Pivotal Metals Limited (ASX:PVT), an explorer and developer in Quebec, Canada, released the first scoping study for its Horden Lake copper project in late September 2026. The study models a conventional open pit and a processing plant producing separate copper and nickel concentrates. It was supported by a resource upgrade earlier in the year and by metallurgical work reporting copper recoveries above 90%.

Base Case and Spot Case

At a base case copper price of US$5.50 per pound, the study estimates a post-tax NPV at a 7% discount rate of A$920 million, an internal rate of return of 49% and payback of 1.3 years from first production. At spot-price assumptions of about US$6.78 per pound, the estimates rise to an NPV of about A$1.34 billion, an IRR of 63% and payback of about one year. Pivotal Metals (ASX:PVT) reports all-in sustaining cost of US$1.00 per pound after by-product credits.

Project Design and Capital

The study assumes a single open pit with truck and shovel Mining and a plant treating 3.5 million tonnes a year, over an initial life of about 10 years. Modelled output is around 247,000 tonnes of copper equivalent over that period. Net pre-production capital is A$411 million, which includes A$75 million of contingency. Pivotal Metals (ASX:PVT) has described Horden Lake as a shallow, high-grade copper deposit that benefits from its location in Quebec, a Jurisdiction with established infrastructure.

Resource and Confidence

The mineral resource is 52.4 million tonnes at 1.05% copper equivalent, containing 549,000 tonnes of copper equivalent, of which 24.3 million tonnes is in the Measured and Indicated categories. About 30% of the study's net smelter return comes from Inferred material, which carries lower geological confidence. The study has no ore reserve and is a Class 5 estimate, with an accuracy range of minus 30% to plus 50%. It is the first economic assessment Pivotal Metals (ASX:PVT) has published for the project.

Next Steps

Further work is expected to include resource growth drilling, additional metallurgical testwork, environmental baseline studies and more detailed engineering. Pivotal Metals (ASX:PVT) also continues drilling at its Belleterre project area in Quebec, which targets copper-gold mineralisation. Financing a project with capital of A$411 million would require substantial external funding, and the Economics will vary with copper prices, exchange rates and technical outcomes in later studies.

Key Insights

The scoping study gives Pivotal Metals (ASX:PVT) a first set of economics for Horden Lake, with strong modelled returns at the assumed copper price and a large funding requirement. Its Class 5 accuracy, reliance on Inferred material and absence of a reserve mean the figures are indicative until further studies are completed.