Highlights

  • Minbos has received the first drawdown of approximately US$2.2 million from the BFA construction facility, with funds applied directly to construction contractors and suppliers.
  • An initial Mining campaign at the Cácata deposit has been completed, stockpiling 23,495 tonnes of phosphate rock for commissioning of the Subantando Beneficiation Plant.
  • A second IDC utilisation claim of approximately US$2.8 million has been lodged with the Industrial Development Corporation of South Africa under the existing Debt facility.
  • The company continues to target commissioning of the Cabinda Phosphate Project in Q2 2027, with construction fabrication in Portugal nearing completion.

Minbos Resources Limited (ASX:MNB), an ASX-listed phosphate developer advancing the Cabinda Phosphate Project in Angola, has announced a series of meaningful operational and financing milestones. The company has received the first drawdown under its Banco de Fomento Angola construction facility, completed its initial mining campaign at the Cácata phosphate deposit, and lodged a second utilisation claim with the Industrial Development Corporation of South Africa. Together these developments reflect the project's continued progress toward its targeted commissioning date.

Minbos confirmed the receipt of the first drawdown of approximately 1.97 billion Angolan kwanza, equivalent to approximately US$2.2 million, from the BFA construction Facility on 18 November 2026. The funds were directed immediately to construction contractors and suppliers, consistent with the terms of the facility and the project's construction programme. This first drawdown marks the activation of the Angolan bank financing Tranche within the broader project debt structure.

In parallel, the company lodged its second utilisation claim with the Industrial Development Corporation of South Africa on 11 November 2026 under the existing IDC debt facility, for approximately US$2.8 million. These two financing actions demonstrate the multi-lender structure supporting the Cabinda project and reflect the continued engagement of Angolan and South African development finance institutions with the project.

Cácata Mining Campaign and Subantando Construction

An initial mining campaign at the Cácata phosphate deposit has been successfully completed, with 23,495 tonnes of phosphate rock now stockpiled on site. Mining was completed on 31 October 2026 and the mining contractor demobilised on 2 November 2026. The campaign included access-road construction, site clearing, topsoil removal, overburden stripping and phosphate extraction. The stockpiled material is intended to serve as feedstock for commissioning of the Subantando Beneficiation Plant.

Construction at the Subantando site continues with fabrication in Portugal nearing completion. The company received a site visit from representatives of Stelo and the IDC during the reporting period, providing an opportunity to review construction progress and discuss the next stages of project development. The visit reflects continued active engagement from key project Stakeholders as Minbos advances toward commissioning.

Marketing Appointment and Field Trials

Minbos has appointed Corentin Rault as Marketing and Sales Manager, joining the company from Timac Agro. Mr Rault brings experience in phosphate rock application in fertiliser Manufacturing and a solid understanding of the broader phosphate market, adding commercial capability as the company moves toward production and market access.

The company is also advancing seven large field trials with established farms in the region, testing its granulated fertiliser product. These trials are an important part of building the market foundation for the project's output and demonstrating the efficacy of the Cabinda product to potential customers in Angola and the broader region.

Key Insights

Minbos Resources is making tangible financing and operational progress at the Cabinda Phosphate Project, with the first BFA drawdown converting project finance structure into active construction capital. The completion of the initial mining campaign and the creation of a phosphate rock stockpile ahead of commissioning provide early-stage operational credibility. The addition of a dedicated marketing and sales function signals the company's focus on commercial readiness alongside engineering execution as it targets Q2 2027 commissioning.