Key Highlights

  • Redstone Resources progressed desktop studies and field programme planning across its Western Australian gold and critical minerals portfolio.
  • Reconnaissance at Mt Cauden included site traverses and drone-based photogrammetry across areas inaccessible on foot.
  • A 3,300-metre reverse circulation campaign at West Musgrave is planned for the March 2027 quarter.
  • The company reported AUD 391,000 in cash and cash equivalents at the end of September.

Redstone Resources (ASX:RDS) explores for copper, gold and other minerals in Western Australia. Its September quarterly report, released on 30 October 2026, outlined work on recently acquired project areas, assessment of environmental and native title requirements and preparations for drilling at West Musgrave. Several proposed programmes remain subject to scheduling and approvals.

Rudall East and Cockatoo Rocks preparations

In June 2026, Redstone entered into an exclusive agreement to acquire interests in a portfolio of Western Australian exploration projects. During the September quarter, work focused on prioritising exploration programmes across the portfolio. The Rudall East project covers 58 square kilometres of granted tenure in the East Pilbara, south of Karlamilyi National Park.

At Rudall East, the company began desktop studies and assessment of native title obligations. Preliminary rock-chip and soil sampling is proposed across selected areas, including identified electromagnetic anomalies. Fieldwork is planned during the December 2026 and/or March 2027 quarters.

The Cockatoo Rocks lithium pegmatite project lies approximately 100 kilometres northeast of Kalgoorlie. Work during the reporting period included desktop review of historical drilling and native title requirements. Redstone is preparing a reconnaissance rock-chip and soil sampling programme targeting lithium-caesium-tantalum pegmatites in the area.

Mt Cauden and Twin Hills drilling preparations

Mt Cauden covers more than 40 square kilometres in the Southern Cross district. A programme of work has been approved for initial Reverse Circulation Drilling at selected gold targets. During the September quarter, an optional additional aircore programme was also approved to investigate geology beneath cover in the eastern portion of the project.

Preliminary reconnaissance involved traversing areas to assess access, geological exposure, surface cover and available sampling material. Drone photogrammetry was completed in locations that could not be accessed on foot. Environmental management requirements for potential drilling remained under assessment.

The Twin Hills gold project in the Menzies district covers 60 square kilometres. A programme of work has been approved for first-phase reverse circulation drilling. During the quarter, Redstone continued reviewing environmental management requirements in preparation for planned activities.

Saturn and West Musgrave exploration schedule

The Saturn project covers 330 square kilometres in the Giles Intrusive Complex. Redstone continued assessing native title requirements and potential first-pass ground activities. Its exploration targets include platinum group element reefs and layered mafic intrusions associated with copper, nickel and cobalt.

At the West Musgrave copper project, planning continued for a proposed 3,300-metre reverse circulation campaign. Selected targets include EM5, East Cigar, West Cigar and Hiding Maggie within the northeastern corridor of the Tollu copper deposit. The drilling campaign is now planned for the March 2027 quarter, subject to approvals, weather and traditional owner Business requirements.

The programme is eligible for a co-funded exploration drilling grant of up to AUD 230,000. This amount represents the maximum grant assistance identified in the quarterly announcement.

September quarter cash movements

The accompanying Appendix 5B showed operating cash outflows of AUD 92,000 and investing cash outflows of AUD 72,000 for the three months ended 30 September 2026. Financing activities accounted for a further net outflow of AUD 2,000. Cash and cash equivalents at the end of the period stood at AUD 391,000.

The reported spending occurred while the company was undertaking desktop assessments, reconnaissance and preparation for proposed field campaigns. The March quarter West Musgrave schedule remains conditional rather than a confirmation that drilling has commenced.

Redstone’s near-term exploration activities encompass reconnaissance, regulatory preparations and proposed drilling across several Western Australian projects. The quarterly update distinguishes completed preparatory work from field programmes scheduled for the December 2026 and March 2027 quarters.