Key Highlights

  • Emerald Resources (ASX:EMR) reported 20,280 ounces of September quarter gold production at Okvau.
  • Okvau All-In Sustaining Cost increased to US$1,210 per ounce.
  • Dingo Range progressed site works and procurement for the processing plant.
  • Memot advanced resettlement and resource work ahead of a maiden ore reserve.

Emerald Resources (ASX:EMR) advanced work on gold developments in Western Australia and Cambodia during the September 2026 quarter. Its operating mine, Okvau, produced less gold than in the June quarter while the company maintained the mine’s full-year guidance.

Okvau production and unit costs

The Cambodian mine produced 20,280 ounces, compared with about 27,100 ounces in the June quarter. All-in sustaining cost rose to US$1,210 per ounce from US$818. Emerald maintained FY27 production guidance of 100,000 to 115,000 ounces and cost guidance of US$980 to US$1,080 per ounce.

Work on the next two developments

At Dingo Range, Emerald progressed site infrastructure, began airstrip construction and ordered further long-lead plant equipment. In Cambodia, the company said Memot had secured the regulatory approvals required for development and operation. Resettlement had advanced and close-spaced drilling was being used to inform the first ore reserve.

What Company Does

Emerald Resources produces gold at Okvau in Cambodia and is advancing Memot in Cambodia and Dingo Range in Western Australia. The company uses its operating mine as a source of current production while preparing other projects that could add output later. Dingo Range is advancing through equipment and infrastructure work, while Memot is moving through resettlement and resource definition needed to support the first reserve.

Risks to Weigh

Lower Okvau production and higher costs could limit cash generated while the company develops its other projects. Memot and Dingo Range each have separate delivery risks. Capital demands from the two developments can overlap with changes in output and unit costs at Okvau. Mine performance may recover unevenly if grade, throughput or sequencing changes from quarter to quarter. Development schedules can also move if contractor, equipment or site access milestones shift.

What to Watch Ahead

Compare Okvau production and costs with FY27 guidance, track plant and infrastructure work at Dingo Range and look for a first ore reserve at Memot. Review subsequent quarterly output and cost figures at Okvau against the full-year ranges. For the development projects, monitor capital commitments along with physical milestones such as infrastructure delivery and drilling that supports the mine plan. The timing of these commitments matters to group cash flow.