Highlights

  • BHP (ASX:BHP): The November site tour outlines a phased copper growth programme.
  • The first phase targets approximately 500,000 tonnes of annual copper production by 2035.
  • A subsequent phase envisages approximately 650,000 tonnes annually by 2040.
  • The programme includes underground Mining expansion and additional smelting capacity.

BHP (ASX:BHP) is a diversified resources company producing commodities including copper and iron ore. Its 23 November 2026 Copper South Australia presentation outlines a two-phase expansion of mining and processing capacity. The programme links prospective production increases with a sequence of Investment decisions and infrastructure requirements extending into the next decade.

Copper production and development phases

The South Australian Business includes Olympic Dam, Carrapateena and Prominent Hill. The FY26 production base provides the starting point for the proposed expansion. The company’s strategy outlines approximately 500,000 tonnes annually by 2035 and approximately 650,000 tonnes by 2040.

These are forward-looking production levels rather than committed annual output. The first phase combines additional mining capacity with processing infrastructure, while the later phase involves further development options. The sequence allows investment decisions to be made at different stages.

Underground mining and processing projects

The Carrapateena expansion involves block caving beneath the existing sublevel cave operation. At Olympic Dam, proposed mine and concentrator development would support an expanded underground mining platform. Prominent Hill’s expansion also forms part of the programme.

Additional ore extraction requires sufficient processing capacity. The proposed smelter and refinery expansion is therefore connected to the mining developments. Coordinating commissioning and ramp-up across different facilities is necessary for the production targets to be achieved.

Investment discipline and infrastructure

The November presentation identifies an indicative internal rate of return of 14–17% for the first phase. This is a programme estimate based on assumptions and is not a realised return. Capital expenditure, operating costs and Commodity prices can affect the eventual result.

Water Supply also forms part of the enabling infrastructure. The presentation identifies Northern Water as a planned multi-user facility, with a potential investment decision in 2027 and first water targeted for FY32. These dates remain forward-looking.

Longer-term development choices

The second phase involves potential additional underground resource development. Selection of a development option and subsequent investment approval depend on technical assessment and commercial conditions. The programme’s copper-equivalent production figures also incorporate by-products and should not be read as copper-only tonnage.

The presentation also identifies potential copper-equivalent output of around 800,000 tonnes annually by 2035 and about one million tonnes by 2040. Copper-equivalent production is a separate measure that expresses the contribution of by-products on a common basis. Prominent Hill’s planned transition towards shaft hoisting is another element of the first-phase programme. The development sequence also incorporates major smelter maintenance and preparatory work, illustrating the importance of coordinating upgrades with existing operations.

Key Insights

The South Australian expansion links underground development with processing and enabling infrastructure. Its staged targets depend on technical studies, capital decisions and coordinated project delivery.