Highlights
- BHP (ASX:BHP) presented a two-phase plan for its South Australian copper operations on 23 November 2026.
- The first phase targets approximately 500,000 tonnes of annual copper production by 2035, subject to project development decisions.
- The proposed smelter expansion would increase concentrate processing capacity to approximately 1.1 million tonnes annually during the first phase.
- The second phase considers additional underground Mining Options and a further increase in smelting capacity.
BHP (ASX:BHP) is a diversified resources company whose operations include copper and iron ore mining. Its South Australian copper portfolio combines Olympic Dam, Carrapateena and Prominent Hill. The November 2026 site tour detailed how additional underground mining capacity and processing infrastructure could support higher output over the next two decades.
A Two-Phase Copper Production Pathway
The expansion strategy starts from a FY26 production base of approximately 320,000 tonnes of copper. Management envisages a rise to around half a million tonnes annually by 2035, followed by a potential increase to 650,000 tonnes by 2040. These figures are prospective production levels, not annual commitments.
The initial programme combines the Prominent Hill expansion with additional development at Carrapateena and Olympic Dam. Its production profile also accounts for the eventual reduction in output from Carrapateena’s existing sublevel cave. This distinction matters because new capacity must replace some existing production before contributing to overall growth.
Olympic Dam Mine and Concentrator Studies
A proposed underground block cave at Olympic Dam would expand the scale of extraction and support more extensive use of the mineral deposit. Block caving is a mining method that relies on the controlled collapse of ore into underground extraction points. The approach requires substantial preparatory development before production can increase.
One configuration under study has an indicative Capital cost of USD 4.1–5.4 billion in real terms as at 1 July 2026, with a potential final Investment decision in calendar 2029. The corresponding study envisages initial production in FY34. BHP is also evaluating alternative configurations with different cave sizes and concentrator schedules.
Smelting Capacity and Infrastructure Dependencies
The first stage of the smelter and refinery expansion carries an indicative capital cost of USD 3.2–4.1 billion. The proposed decision window is the second half of calendar 2027, with initial production envisaged in FY32. The development would add a smelting furnace and acid plant while expanding refining facilities.
The processing programme is designed alongside the mine expansions rather than as an isolated investment. Under the first phase, some copper would be sold in concentrate instead of being refined into cathode at the site. Water availability, power upgrades and supporting infrastructure are important to the sequencing of the broader development programme.
Longer-Term Underground Development Options
The second phase incorporates potential development at Ankata or future Olympic Dam block caves, including Olympic Dam Deeps. A further smelter expansion could lift annual concentrate capacity to between 1.4 million and 1.7 million tonnes. The eventual processing configuration would depend on the scale and timing of mine development.
The projects are at different stages of technical assessment. Capital estimates, construction schedules and operating assumptions remain subject to refinement as studies progress. The timing of investment decisions therefore matters as much as the production ambitions, particularly where one project relies on infrastructure established by another.
Key Insights
The South Australian programme combines mine expansion and processing investment within a staged development plan. Its longer-term production ambitions depend on individual project approvals, technical outcomes and the timely delivery of enabling infrastructure.