Highlights
- BHP (ASX:BHP) outlined its two-phase Copper South Australia growth strategy on 23 November 2026.
- Annual copper output could reach approximately 500,000 tonnes by 2035 under the first phase.
- Proposed investments include mine expansions and additional smelting and refining capacity.
- Ankata and Olympic Dam Deeps remain alternative development Options for the second phase.
BHP (ASX:BHP) is a diversified resources company with Mining operations spanning commodities including copper and iron ore. Its November 2026 South Australian site tour outlined a coordinated expansion of underground mining and processing infrastructure, with potential annual copper production of up to 650,000 tonnes by 2040. The proposed developments remain subject to further assessment and Investment decisions.
Copper Production Targets Across Two Phases
Copper South Australia produced 321,000 tonnes in FY26, representing a 2% year-on-year increase. The July operational review attributed the improvement to mining and milling performance, alongside the effect of a weather-related power interruption in the previous reporting period. BHP has subsequently outlined a pathway towards annual production of approximately 500,000 tonnes by 2035.
The longer-term plan envisages output of up to 650,000 tonnes annually by 2040. The strategy involves a greater contribution from block caving, an underground mining method that allows large volumes of ore to be extracted. Its application forms part of the company’s proposed approach to increasing output while managing mining costs. The figures represent prospective production levels rather than committed annual volumes.
Carrapateena and Olympic Dam Investment Options
The Carrapateena expansion has an indicative Capital requirement of USD 1.8–2.1 billion, with a potential investment decision in the first half of calendar 2028. The proposed development would introduce block caving below the existing sublevel cave operation.
At Olympic Dam, BHP is studying mine and concentrator expansion options. One development configuration has estimated Capital Expenditure of USD 4.1–5.4 billion, with an investment decision potentially occurring in 2029. The studies consider how underground extraction capacity and ore processing could be expanded together. Capital estimates are expressed in real terms as at 1 July 2026 and remain subject to further study.
Smelting Capacity and Processing Infrastructure
The first stage of the proposed smelter and refinery expansion carries an indicative cost of USD 3.2–4.1 billion. BHP identifies the second half of calendar 2027 as the potential timing for a final investment decision.
The proposed configuration includes an additional smelting furnace, an acid plant and expanded refining capacity. Coordinating these developments with mining and concentrator projects is important because additional ore extraction does not automatically translate into equivalent increases in refined copper production. The company also identifies water and power infrastructure as enabling elements of its broader expansion strategy.
Ankata Exploration and Longer-Term Development
Ankata, previously named Oak Dam, has a reported mineral resource containing 8.8 million tonnes of copper. An updated resource estimate is expected in calendar 2027. The resource figure is not equivalent to an economically recoverable reserve.
BHP identifies either Ankata or Olympic Dam Deeps as a potential second-phase development, with indicative capital expenditure of USD 4.5–5.8 billion and a possible investment decision in 2032. Project selection, technical studies and future approvals remain relevant to the timing and scale of this expansion.
Key Insights
The South Australian strategy links mine development with processing capacity over an extended investment timetable. Its production targets remain conditional on technical assessment, infrastructure delivery and separate capital approval decisions.