BCI Minerals (ASX:BCI) is developing the Mardie Salt and Potash Project on the Pilbara coast of Western Australia. The project reached 85% completion during the June 2026 quarter, with salt crystallisation underway and first shipment targeted for the first quarter of 2027.
What Just Happened?
BCI's June 2026 Quarterly Report stated that Mardie was 85% complete, with cumulative expenditure of approximately A$1.185 billion against a salt-first budget of A$1.443 billion.
Salt crystallisation had commenced, with approximately 49,000 tonnes formed by the end of June. By 20 July, reported salt inventory had increased to about 82,000 tonnes, while pond levels had reached approximately 98% of their design operating height.
During the March quarter, cyclones Mitchell and Narelle caused heavy rainfall that diluted pond densities and delayed crystalliser lining work. BCI reported that the project's infrastructure was not materially damaged.
The Company and Its Key Assets
BCI Minerals was formerly known as BC Iron and has historically generated income from its Iron Valley iron ore operation in Western Australia.
Its principal development is the Mardie Salt and Potash Project near Karratha. Mardie is designed to produce salt using seawater evaporation through solar and Wind Energy .
The project also includes a proposed sulphate of potash (SOP) operation. BCI has awarded front-end engineering work for the SOP facilities to Bluestar and has been operating trial crystallisers. A board Investment decision for the SOP project was scheduled for August 2026.
Mardie Development
Mardie is being developed as a large-scale solar salt operation with associated port infrastructure.
The project uses evaporation ponds and crystallisers to produce salt from seawater. The company has targeted the first salt shipment for the first quarter of 2027, subject to evaporation conditions and completion of the required infrastructure.
The marine package was scheduled for completion around September 2026. The salt wash plant and crystalliser lining were targeted for completion around March 2027.
Key Development Factors
Mardie's production schedule is affected by weather conditions, particularly rainfall, temperature and wind. Heavy rainfall can dilute pond densities and extend evaporation periods.
BCI also continues to fund construction while carrying project Debt . The company has indicated that its debt facilities extend into the 2030s.
Salt prices and Demand are additional commercial factors. BCI has cited Asian salt demand growth and new global Supply developments in its project materials.
The proposed SOP operation would require additional Capital following a final investment decision.
BCI has also discussed potential third-party use of Mardie's port infrastructure for iron ore exports. Any such use would depend on commercial arrangements and required approvals.
What Comes Next?
The next development milestones include:
- A decision on the SOP project.
- Completion of the marine package.
- Continued construction and commissioning at Mardie.
- Completion of the salt wash plant and crystalliser lining.
- First salt shipment, currently targeted for the first quarter of 2027.
- Further updates on project expenditure, production and financing.
The timing of first shipment remains dependent on construction progress and evaporation conditions.
Conclusion
BCI Minerals' Mardie Salt and Potash Project reached 85% completion by the June 2026 quarter. Cumulative expenditure was approximately A$1.185 billion against a salt-first budget of A$1.443 billion.
Salt crystallisation had commenced, with approximately 49,000 tonnes formed by the end of June and reported inventory of about 82,000 tonnes by 20 July.
The project remains under construction, with first salt shipment targeted for the first quarter of 2027. Further milestones include marine infrastructure completion, salt-processing facilities, crystalliser work and a proposed investment decision for the SOP project.