Highlights
- Aura Energy (ASX:AEE) outlines post-tax NPV of US$500.3 million and a 28% post-tax IRR for the Tiris uranium project.
- The Tiris Ore Reserve is 37.3 Mlb U3O8, up 11%, with development Capital estimated at US$349.8 million.
- A final Investment decision is targeted for December 2026, with first ore at the end of 2028.
- Cash was A$10.6 million at 30 September 2026, and the US$400 million funding plan is not yet secured.
Aura Energy Limited (ASX:AEE) is an Australian-based uranium development company listed on the ASX and AIM, with its flagship Tiris Uranium Project in Mauritania and the Häggån polymetallic project in Sweden. In the 24 November 2026 session, shares were priced at AUD 0.063, up 5.00%. Recent company disclosures cover updated Tiris study results, a staged funding plan and pilot plant work ahead of a targeted investment decision.
Tiris and Häggån: Business Overview
Aura owns 85% of Tiris, with the remaining 15% held by the Mauritanian State through ANARPAM and free-carried through construction. The project hosts a Mineral Resource of 91.3 Mlb of U3O8 and an Ore Reserve of 37.3 Mlb, which the company reports as 11% higher following its 2026 bankable feasibility study. Aura also holds 100% of Häggån in Sweden, a polymetallic project whose Inferred uranium resource is being converted from the JORC 2004 to the JORC 2012 code. Sweden's uranium Mining ban was lifted, with the legislation taking effect in July 2026.
Study Outcomes and Project Economics
The 2026 study describes production of about 1.8 Mlb per year, with 46.1 Mlb of saleable uranium over a 26-year mine life following about two years of construction. At a uranium price of US$90 per lb, post-tax NPV at an 8% discount rate is US$500.3 million on a 100% ungeared basis, or US$425.3 million attributable to Aura shareholders. The post-tax unlevered IRR is 28% and payback is 3.2 years from first production.
Development capital is estimated at US$349.8 million, with a Class 3 accuracy range of plus or minus 15% and contingency of 11%. Life-of-mine capital is US$573.3 million. C1 cash cost is US$32.53 per lb and All-In Sustaining Cost is US$41.25 per lb. Aura reports that NPV changes by about US$139 million for each US$10 per lb movement in the uranium price. About 33% of scheduled ore comes from Inferred Mineral Resources, and an Ore Reserve-only case gives an NPV of US$355.3 million and an IRR of 25%.
Funding Plan and Approvals
ASX:AEE has set out a US$400 million funding plan that has not been secured. It assumes US$220 million of senior and subordinated debt, including advanced discussions with the US International Development Finance Corporation on US$150 million to US$170 million of senior debt, and US$180 million of Equity or quasi-equity. The company reports a non-binding memorandum of understanding with a nuclear Utility and a non-binding proposal from a US investment fund. It also reports a A$20 million Placement secured with institutional investors.
Several Mauritanian approvals are in place, including exploitation permits valid to February 2049 and a 2024 authorisation for uranium mining and production. Water, power, transport and export permits remain outstanding and are expected through 2027. Fiscal terms include a 25% corporate tax rate after a 36-month holiday and a 3.5% Royalty on free-on-board value. Offtake is contracted with Curzon at 300,000 lb per year for seven years, leaving about 83% of output uncontracted.
Financial Position and Uranium Sector Context
Aura reported cash of A$10.6 million at 30 September 2026. As a pre-production company, ASX:AEE does not report Operating Revenue from Tiris, and its financing depends on the funding plan above. Uranium development Economics are sensitive to long-term contract pricing, power costs and capital costs. Aura's study uses a life-of-mine realised price of US$89.3 per lb, and it notes that power pricing and the power purchase agreement are not finalised, with the agreement expected in the first quarter of 2027.
Risks to Consider
For ASX:AEE, the company states that no lender or investor has committed to the funding plan and that equity raising may dilute existing shareholders. Other risks include the remaining permits, the conversion of Inferred resources through infill drilling, capital cost accuracy, power pricing and uranium price movements. The Häggån resource remains Inferred until the JORC 2012 conversion is complete.
What to Watch Next
Pilot plant testing at Bir Moghrein is scheduled to run about 80 tonnes of Tiris ore from November 2026, with testing complete in December 2026. A final investment decision is targeted for December 2026. Construction start and the power purchase agreement are both expected in the first quarter of 2027, transport and export approvals through 2027, first ore at the end of 2028 and nameplate production in 2030.
Key Insights
Aura Energy (ASX:AEE) has published updated Tiris economics, a larger Ore Reserve and a staged plan toward an investment decision. Funding, permits and pilot plant results are the main variables between the study and construction, while uranium prices and power costs influence project returns.