The program ran from 30 July to 16 September 2026 and covered Dulcie Central, Water Bore, Scott's Grey and Dulcie South. It included the first drilling on mining lease M77/599, acquired on 29 April 2026, which spans the roughly 600 m corridor between the …
Green hosts an Inferred Mineral Resource of 19Mt at 1.6% Nb2O5 above a 1.0% cut-off, nested within 100Mt at 0.71% Nb2O5 above a 0.25% cut-off. Shallow aircore drilling is being used to locate high-grade zones before diamond holes define the full vertical extent of …
The Edna May acquisition includes a fully permitted 2.9Mtpa processing facility, associated infrastructure and a regional landholding. Forrestania began integration, mine planning and operational readiness work after completion, with gold production scheduled to start in the December 2026 quarter. Payment for the project comprised …
The estimate, announced on 15 July 2026, was prepared by independent consultant Placer Consulting, with variography and peer review by Datamine Australia. All mineralisation is classified as Inferred. At a 0.7% rutile cut-off the resource is 298Mt at 0.87% rutile and 1.19% total graphitic …
ALS Metallurgy Pty Ltd carried out the test work on a single bulk composite taken from a continuous twelve-metre interval between 147 and 159 metres in diamond hole 26NRDD525, within the disseminated sulphide zone. The composite assayed 2.05 g/t palladium, 0.43% copper, 0.39% nickel, …
The testwork was carried out at ALS Metallurgy in Perth under the supervision of Mining One Consultants, using composites of drill core and channel samples. Head grades were 0.97 g/t Au for the Fresh composite, 1.29 g/t for Transitional and 2.89 g/t for Channel, …
Total production of 76.1kt compared with 58.0kt in the June quarter and 123.8kt a year earlier, when synthetic rutile was still being made. The September quarter output comprised 25.6kt of zircon sand, 29.3kt of zircon-in-concentrate and 21.2kt of rutile. Both synthetic rutile kilns remained …
Mount Ida holds a resource of 1.85B tonnes at 29.48% Fe on a granted mining lease, which Juno describes as the largest magnetite resource in the Yilgarn region. The Central Zone totals 1,231 million tonnes at 29.79% Fe, including 463 million tonnes of magnetic …
The quarter included $35.1 million of revenue received, inclusive of GST and unaudited, against approximately $7.6 million spent on direct operating costs. Over its life the pit yielded 303,437 tonnes at 1.68 g/t Au, with 14,910 oz of gold sold at 91% metallurgical recovery. …
Ore mined rose 5.95% to 212,259 tonnes at 1.69% Sn, up from 1.58%, as a larger share of Area 5 ore entered the mix. Ore milled fell 6.79% to 171,272 tonnes at 2.02% Sn, and mill recovery was 77.14% against 78.55%. Crusher utilisation was …