Key Highlights

  • Boss Energy Limited (ASX:BOE) released its 2026 Annual General Meeting addresses on Wednesday 25 November 2026, with new Chair Peter Botten acknowledging Shareholder disappointment after the December 2025 Withdrawal of the Honeymoon Enhanced Feasibility Study and the resulting share price fall.
  • Honeymoon production up 61% to 1.41 million pounds of drummed U₃O₈, meeting revised guidance.
  • Revenue of A$151.1 million (FY25: A$75.6 million).
  • Net profit after tax of A$2.5 million.

Boss Energy Limited (ASX:BOE) released its 2026 Annual General Meeting addresses on Wednesday 25 November 2026, with new Chair Peter Botten acknowledging shareholder disappointment after the December 2025 withdrawal of the Honeymoon Enhanced Feasibility Study and the resulting share price fall. The uranium producer used the meeting to outline FY26 results, FY27 guidance, its New Feasibility Study for Honeymoon in South Australia and a longer-term regional hub plan. The addresses may draw attention as the company attempts to rebuild market confidence after a difficult period.

What did Boss Energy announce?

Mr Botten, at his first AGM as Chair, said a Honeymoon Review found the earlier study's assumptions were not supported by updated drilling and operating data, leading to a significant cut in the Honeymoon Mineral Resource. He said leadership, technical capability and systems had been strengthened, and that "Shareholder confidence will be rebuilt through results."

For FY26, the company reported:

Honeymoon production up 61% to 1.41 million pounds of drummed U₃O₈, meeting revised guidance

C1 cash cost of A$39/lb and All-In Sustaining Cost (AISC) of A$61/lb

Revenue of A$151.1 million (FY25: A$75.6 million)

Net profit after tax of A$2.5 million

Operating cash flow of A$73.6 million (FY25: A$17.4 million)

FY27 guidance is production of 1.25–1.30 million lbs, C1 cost of A$51–56/lb, AISC of A$83–92/lb and capex of A$58–65 million. In Q1 FY27 the company drummed 359,000 lbs at C1 of A$47/lb and AISC of A$79/lb, with a realised price of A$117/lb (US$82/lb). The quarter lost 19 days to rain, and FY27 was described as a transition year.

The New Feasibility Study, released on 27 August 2026, uses wide-spaced wellfields with about 50% less wellfield infrastructure. It outlines about 13.8 million lbs over nine years to at least FY34, ramping to a steady rate of about 1.9 million lbs a year in FY30–33, at a life-of-mine average AISC of A$79/lb (US$55/lb).

Related Sector Context

Energy businesses operate within markets shaped by Commodity demand, Supply availability and infrastructure. Project development and production require capital, technical capability and regulatory approvals; realised prices and operating costs influence the funds available for reinvestment.

Risks to Watch Out

The regional hub concept adds Jason's Deposit (12.0 million lbs) and Gould's Dam (33.1 million lbs) to Honeymoon's 20.8 million lb resource. The company stated its aspiration of 2.5 million lbs a year at about A$65/lb AISC by the early 2030s is not a Production Target and that it does not yet have reasonable grounds to believe it can be achieved.

Realised commodity prices, operating reliability and expenditure requirements can affect cash generation. Changes in production assumptions or the timing of field work may alter the funds available for development. Regulatory approvals, logistics and access to financing can also influence whether planned milestones are achieved within the expected timeframe.

Changes in commodity pricing and production costs could affect cash generation. Delays in approvals, construction or commissioning may defer Revenue while expenditure continues. Financing terms and access to infrastructure could also constrain the timing of future investment.

What should investors watch next?

Key items flagged include the wellfield schedule, with EKT1 leaching from Q2 FY27, HMT1 in Q3 FY27, EKT2 in Q4 FY27 and EKT3 in Q1 FY28. Investors may also watch quarterly delivery against FY27 guidance, environmental referrals for Jason's and the Honeymoon Mine Extension, and progress at the 30%-owned Alta Mesa joint venture in Texas, which the company said has not yet delivered the outcomes originally expected.

Safety is another area: Honeymoon's 12-month rolling TRIFR rose to 19.7 at Q4 FY26 before easing to 17.8 at Q1 FY27. The Board also expects to add Mining and commercial expertise within 12 months.