Highlights

  • Evion Group (ASX:EVG) reported engagement with Madagascan officials and prospective finance participants concerning its Maniry graphite project.
  • The company previously secured Mining permits for Maniry and is working towards remaining approvals and a final Investment decision.
  • An August commercial arrangement envisages at least 10,000 tonnes of graphite concentrate annually for five years from first production.
  • Recent funding discussions were described as non-binding, leaving project financing and construction timing unresolved.

Evion Group (ASX:EVG) develops graphite and other industrial mineral interests, including the Maniry project in southern Madagascar. Its November 2026 update outlined meetings about project financing, government requirements and commercial processing opportunities. Although mining permits and prospective customer arrangements provide a basis for further work, the project has not reached a final investment decision.

Government Engagement and Permit Status

Evion reported discussions in Antananarivo with Madagascan government representatives concerning the path to development of Maniry. These followed the granting of key mining permits in July 2026. Mining tenure does not resolve every project requirement: the company identified remaining environmental, commercial and administrative matters before construction can be authorised. Meetings also involved German and European representatives on possible local processing, grants and Training opportunities. Such discussions indicate the subjects under consideration, but do not themselves prove that additional permits, grants or processing ventures have been finalised. The timing of the remaining approvals is therefore an important Factor in the project schedule.

Offtake Agreement and Proposed Output

The company has described an August binding offtake terms sheet with a German customer covering a minimum of 10,000 tonnes of natural flake graphite concentrate per year for five years from production commencement. The planned first-stage operation is designed to produce approximately 39,000 tonnes annually, making that contracted quantity only part of envisaged output. Pricing terms include a market reference and a cost-linked floor mechanism, subject to the agreement’s terms. Importantly, contractual purchase arrangements depend on production beginning and product meeting relevant conditions. They should not be mistaken for current mining Revenue or a guarantee that financing will be arranged.

Financing Discussions and Strategic Context

Evion said it engaged prospective financiers and institutional representatives, including participants associated with Madagascar’s sovereign investment structures. The company also described discussions with an African financial institution about support for a government levy and potential development costs. These proposals were not presented as binding Credit commitments. Maniry’s designation as a strategic project under the European Union’s critical raw materials framework may be relevant to potential permitting and funding pathways, but the status does not itself establish an approved Loan or grant. A credible funding package would need to address construction, working capital, contingency and repayment requirements.

Next Milestones and Execution Risks

The immediate priorities include closing out remaining regulatory conditions, extending commercial relationships and clarifying project funding. A completed feasibility study and mining permits are significant inputs to planning, but graphite market conditions can change before first production. Processing specifications, logistics in Madagascar and project delivery costs also matter to a development decision. Evion’s broader portfolio includes expandable graphite activities in India, yet those activities should be distinguished from Maniry’s proposed mine development. The next material step will be evidence of enforceable financing and approvals, rather than further expressions of interest alone.

Key Insights

Maniry has mining permits and a prospective offtake framework, but non-binding financing discussions do not constitute construction funding. Outstanding authorisations, contractual commitments and project execution remain decisive considerations.