Key highlights

  • Kalina Power advanced five Alberta projects while investigating opportunities for two more locations for proposed gas-fired power developments.
  • Clairmont moved into the Alberta grid operator’s second cluster, with about CAD 2.6 million posted in security with the grid operator and ATCO.
  • Kalina reported about AUD 11.4 million in cash and no Debt at the end of the September 2026 quarter.

Kalina Power (ASX:KPO) shares rose 7.69% to AUD 0.014 during the Trading session on 23 November 2026. The benchmark S&P/ASX 200 stood at 8,597.80 points at 11:40 am AEDT. Kalina Power is a power project developer with a portfolio of proposed gas-fired plants in Alberta, Canada. Its 30 October 2026 quarterly update outlined progress on grid applications, gas Supply and preparations for proposed large-load connection rules.

Clairmont progresses through the grid queue

Kalina’s Alberta development Subsidiary advanced Clairmont into Cluster 2 of the Alberta Electric System Operator’s connection process. It posted about CAD 2.6 million in security with the grid operator and ATCO. Other projects covered by the update were in Cluster 3 and retained mid-2029 in-service dates. Those dates reflect their position in the process and the company’s planned development schedule.

A separate Cluster 3 application for Saddle Hills requested a 100-megawatt electrical interconnection. Kalina expected the system operator’s review and comments on the proposed connection size before the end of calendar 2026. The company also identified rezoning and gas contracting as milestones before front-end engineering and design.

Kalina reported the projects of about 200 megawatts had already progressed through the operator’s process. Its move to advance Clairmont and post security was a project-level decision within that queue. The Saddle Hills application concerns a separate request at a smaller scale.

Gas availability varies across sites

Kalina continued to approach regulated and unregulated gas suppliers during the quarter. It identified constraints on the regulated supply system for Alsike, Gilby and Myers and was discussing alternatives with gas producers, processors and other potential counterparties. The company described Saddle Hills and Clairmont as being in areas without the same constraints. The five-site portfolio spans different areas of the province, with location affecting gas supply, grid access and zoning.

The company said it was focusing spending on the work needed to clear such project milestones while waiting for the connection rules. It plans to prepare Utility permit applications according to the readiness and funding of individual sites.

Data centre connections in Alberta

Kalina reported power applications from data centres exceeded 16 gigawatts in Alberta. The grid operator published drafts for a large-load process covering requests greater than 75 megawatts, including from industrial users and data centres. The proposed Bring Your Own Generation rules would link a large load applicant to new generation capable of meeting its requested capacity. Kalina participated in a group that contributed to the draft recommendations.

The large-load process would enable the operator to consider both the Demand from an applicant and the supply brought forward to meet that demand. Kalina cited that balance as an element of the draft approach to managing the grid.

Grid rules and permits are still pending

The operator’s rollout of the generation framework had been delayed while it considered feedback. Its stated timetable, as relayed by Kalina on 30 October, was for the documents before the end of the Canadian autumn. The eventual allocation process will shape how large power users and generation developers apply for grid access. Kalina’s projects also depend on site-level work including rezoning, gas procurement and permit applications, which the company intends to prioritise according to each project’s progress and available funding.

What to watch before commercial contracting

The first points to watch are publication of the grid requirements and the operator’s response on Saddle Hills. Kalina expected an initial six-week intake window for applications after publication. The company reported about AUD 11.4 million in cash and no debt at quarter-end, while continuing to engage with financing and potential commercial counterparties. Site and fuel arrangements are other steps in preparing the projects for contracting.

The October report anticipated subsequent intake windows roughly every six to nine months after the initial process.

Two processes running in parallel

The Alberta grid operator is developing rules for connecting large users while Kalina advances individual project sites through grid, fuel and zoning work. The next dates relate to the proposed framework and connection review, ahead of any subsequent commercial arrangements for the power projects.