Norwest Minerals Limited (ASX:NWM) has released results of a Scoping Study for its 100%-owned Bulgera Gold Project in Western Australia, indicating a standalone open-pit mining and on-site heap leach processing operation is technically and economically viable, with a pre-tax NPV of approximately A$89 million at a base case gold price of A$5,800 per ounce.
Key Points
- Pre-tax NPV (7% discount rate) of approximately A$89 million at A$5,800/oz gold, rising to A$139 million at A$6,500/oz, and A$32 million at A$5,000/oz
- Pre-production capital expenditure estimated at A$54 million, incorporating A$3 million contingency, with maximum cash drawdown of approximately A$62 million
- 57-month operational mine life targeting approximately 87,000 ounces of recovered gold at an average of approximately 18,000 oz per year from 6.3 Mt of material
- Approximately 78% of the production target is based on Indicated Mineral Resources and approximately 22% on Inferred Mineral Resources
- The company is advancing into Pre-Feasibility Study workstreams following completion of the Scoping Study
Bulgera Gold Project Location and Scoping Study Parameters
The Bulgera Gold Project is located in the Plutonic Well Greenstone Belt in Western Australia, approximately 200 km north of Meekatharra and 50 km northeast of the Plutonic Gold Mine. The Scoping Study was compiled by Norwest with input from independent specialist consultants including Orelogy Mining Consultants, ALS Metallurgy, Kappes Cassiday & Associates Australia, NewPro Consulting & Engineering Services, and MBS Environmental. All financial figures are reported in real Australian dollars on a pre-tax, ex-GST basis to a Scoping Study accuracy of plus or minus 35%, evaluated at a base gold price of A$5,800 per ounce.
Production Profile and Metallurgical Specifications
The Scoping Study outlines mining of 6.3 Mt of highly weathered oxide and moderately weathered oxide material at an average diluted grade of 0.57 g/t Au over a 57-month mine life, with a life-of-mine strip ratio of 3.1:1. Nominal process plant throughput is 1.5 Mtpa. Conventional heap leaching at a 25 mm crush size is projected to yield a weighted average field recovery of 74%–75% with average cyanide consumption of 0.20 kg/t. The first 12 quarters of processing includes an average of 84% Indicated Resources. Approximately A$6 million in staged sustaining and expansion capital is estimated across Years 2 to 3.
Capital Requirements and Pre-Feasibility Study Workstreams
Pre-production capital of approximately A$54 million covers an owner-operated crushing circuit, processing plant, Stage 1 heap leach earthworks, and site infrastructure. The company disclosed that funding of approximately A$54 million pre-production capital will likely be required to achieve the range of outcomes indicated in the Scoping Study, and noted there is no certainty that funding will be available or that it will not be dilutive to existing shareholders. The company stated it is advancing into Pre-Feasibility Study workstreams, including fine-crush recovery optimisation, infill drilling of Inferred material, evaluating potential inclusion of deeper fresh rock mineralisation, and sampling historic oxide waste dumps.