Latrobe Magnesium Limited (ASX:LMG) has reported that its Phase 1B Project at the Latrobe Valley Demonstration Plant in Victoria is 100% installed, with staged commissioning advanced to 78% completion and furnace heating now under way, as the company remains on track to produce magnesium metal crowns of greater than 98% purity by the end of 2026.

Key Points

  • Phase 1B installation is 100% complete across all work areas, including briquetting plant, furnace and loading equipment at the Latrobe Valley Demonstration Plant.
  • Overall commissioning has advanced from 50% at 31 October 2026 to 78%, with staged furnace heating now commenced.
  • The first batch of magnesium oxide feed briquettes has been produced and is awaiting feed to the retort.
  • Project forecast spend remains within the original A$6.1 million budget, with zero recordable incidents since project commencement.

Phase 1B Installation and Commissioning Progress

According to the filing dated 23 November 2026, all briquetting plant, furnace and loading equipment is in place at the Latrobe Valley Demonstration Plant in Victoria. The final furnace seal was installed following furnace ignition testing. Reagent milling and briquetting commissioning has been completed, with the first batch of magnesium oxide feed briquettes produced and awaiting feed to the retort. Final loading systems testing is occurring in parallel with the furnace heat-up process. Once furnace heat-up is complete, the company said final ore commissioning at the retort will proceed, followed by metal extraction system testing.

First Magnesium Metal Target and Operational Readiness

The filing states that following successful ore commissioning, practical completion can be declared, with subsequent handover to LMG's operations team, positioning the company to achieve manufacture of magnesium metal crowns at greater than 98% purity by the end of 2026. The company disclosed that all key operational roles have been appointed and training has commenced. All reagents required for the four-week operational campaign are on site. Chief Executive Officer Robert Stein said completion of all installation work is a key milestone for LMG to validate its technology for producing magnesium metal.

Budget and Health, Safety and Environment Performance

Latrobe Magnesium disclosed that forecast project spend remains within the original A$6.1 million budget, with remaining spend in line with forecasts outlined in the company's recent equity raising. The filing also reported that the project's Health, Safety and Environment performance has been maintained at zero recordable incidents since project commencement. The company described its HSE performance as continuing at an exceptional standard. No further financial detail beyond the A$6.1 million original budget figure was disclosed in the filing.