Centuria Capital Group (ASX:CNI), together with ResetData Pty Limited — in which Centuria holds a 50% interest — has disclosed a series of operational milestones including a Master Services Agreement with CDC Data Centres, a $165 million GPU bridge financing facility with Macquarie Bank, and the completion of GPU orders for AI Factory 1 Stage 2, according to a company filing dated 13 August 2026.

Key Points

  • Master Services Agreement signed with CDC Data Centres for an initial 7MW allocation, with a Letter of Intent for an increase to 10MW
  • $165 million senior bridge GPU financing facility executed with Macquarie Bank's Specialised and Asset Finance Division
  • 72MW of dedicated power generation units secured for delivery in 2028 with multi-site optionality
  • Remaining GPUs ordered for AI-F1 Stage 2, completing the AI-F1 capacity build-out
  • Customer revenue commencement remains on track for 2H FY27; FY26 guidance re-affirmed

CDC Data Centre Agreement and Capacity Expansion

ResetData has signed a Master Services Agreement with CDC Data Centres, providing an initial allocation of 7 megawatts with a Letter of Intent supporting an increase to 10MW. GPUs have been ordered for a portion of the initial CDC deployment, with revenue anticipated from the initial order in the second half of FY27. The Group has also secured 72MW of dedicated power generation units for a Centuria data centre development, forming part of a broader 250MW-plus infrastructure pipeline. The filing states this fast-tracks long-lead-time infrastructure by approximately two years and provides a pathway for additional customer deployments within Centuria data centres from early 2028. The Group disclosed it has elected not to progress with a previously announced 13MW heads of agreement, citing the identification of alternative opportunities with greater scale and improved long-term economics.

Macquarie Bank GPU Bridge Financing Facility

Centuria and ResetData have executed facility documentation with Macquarie Bank's Specialised and Asset Finance Division for $165 million of senior bridge GPU financing. The filing states the facility complements ResetData's existing Dell Financial Services partnership and supports staged NVIDIA GPU procurement and deployment across Centuria-owned and third-party facilities. Proceeds from the Group's June 2026 equity raising will be used to support parent company guarantees associated with project financing arrangements. Financing for AI-F1 Stage 2 remains in place through Dell Financial Services, supported by a Centuria parent company guarantee.

Customer Demand and AI Factory 1 Deployment Status

A strategic Memorandum of Understanding has been executed with an investment-grade corporation to potentially procure approximately 2MW of capacity in a staged deployment within Centuria-owned data centre facilities. The filing states customer enquiries continue to exceed ResetData's near-term sovereign AI compute capacity, with multiple opportunities progressing through commercial, technical and contracting discussions. ResetData has ordered the remaining GPUs required for AI-F1 Stage 2. Target deployments span three facilities — AI-F1 Stage 2, an existing Centuria facility, and the CDC Master Services Agreement — all with a target revenue commencement period of 2H FY27. Centuria re-affirmed FY26 guidance and disclosed its FY26 annual results are scheduled for Thursday, 27 August 2026.