Key Highlights
- NEXTDC lifted November FY27 net Revenue guidance to A$485 million to A$500 million after cutting its expectations in October.
- Updated underlying EBITDA guidance is A$260 million to A$275 million, with Capital Expenditure guidance unchanged at A$4.5 billion to A$5 billion.
- Guidance continues to exclude revenue and associated EBITDA from M3 customer contracts affected by delayed power supply.
- Most FY27 spending is directed towards delivering contracted capacity, while uncontracted projects and new land purchases remain on hold.
NEXTDC (ASX:NXT) raised its FY27 net revenue and underlying Earnings guidance on 20 November following a project-by-project capital spending review. The data centre operator kept its capital expenditure range unchanged and prioritised delivery of capacity already under contract. The upgrade continues to exclude M3 Melbourne customer contracts affected by delays to power supply.
How the guidance changed
The company forecasts net revenue of A$485 million to A$500 million, up from A$475 million to A$500 million in October. It expects underlying EBITDA of A$260 million to A$275 million, compared with the previous estimate of A$245 million to A$265 million. The net revenue and underlying EBITDA midpoints are 22% and 8% above the corresponding FY26 results, respectively.
NEXTDC attributed the higher revenue floor to trading outside the affected M3 contracts and more certainty around customer delivery timing. The earnings revision also reflects expected cost savings after directing operating spending towards delivering capacity. November’s figures remain below the August ranges of A$615 million to A$640 million for net revenue and A$385 million to A$410 million for underlying EBITDA. Those earlier estimates included the affected M3 contracts.
Which data centre projects receive funding
NEXTDC builds and operates data centres and provides capacity and connectivity to customers who install or use computing infrastructure at those facilities. The group says most FY27 capital spending is directed to existing customer contracts at S4 Sydney, M2 and M3 Melbourne, and KL1 Kuala Lumpur. These represent approximately 600 megawatts of FY26 pro forma contracted utilisation.
S4 had 250 megawatts contracted of a planned 365 megawatts of IT load. Its 115-megawatt first phase was under construction. Across the portfolio, NEXTDC intends to finish and hand over contracted capacity, then start billing customers. New development commitments require customer contracts, sufficiently advanced power and planning, funding, and expected returns above the company’s cost of capital.
Power delays and the Investment timetable
The FY27 spending range includes about A$500 million of reimbursable customer fitout and A$230 million of capitalised interest. NEXTDC says the November review confirmed that, for the most part, spending is committed to capacity in its forward order book, which was 565 megawatts on the FY26 pro forma measure. That order book includes affected M3 contracts, even though November’s earnings guidance excludes their contribution.
The October capital spending revision already removed material discretionary work from the FY27 budget. The remaining programme covers contracted capacity expected to be delivered over the next 12 to 18 months and development work close to completion. NEXTDC also placed new land acquisitions on hold as it prioritises these projects.
NEXTDC said it could not yet reliably estimate the FY27 contribution from those M3 contracts. Its guidance and spending review establish which projects it plans to advance now. Future updates can show when more contracted capacity reaches handover and billing, whether and when M3 can contribute, and how the company progresses its assessment of a possible S4 joint venture.