Key Highlights
- First AI high-performance computing contract (A$8.8 million) cancelled after the customer's post-quarter strategic shift; termination payment of about A$4.2 million expected.
- Second AI contract for A$12.2 million signed in August 2026 with an unnamed operator for a turnkey 2MW Facility targeted for early 2027.
- FY26 Revenue fell 33% to A$10.1 million, though the September 2026 quarter showed recovery with revenue of about A$3.4 million.
- Building new factory capacity to meet a shift in order book Demand toward artificial intelligence workloads.
DXN Limited (ASX:DXN) is building new factories because its modular data centre order book has shifted towards artificial intelligence, even though its first AI contract has just been cancelled. The company lost an A$8.8 million order after 30 September 2026 but is also delivering a larger A$12.2 million one.
What DXN makes
DXN designs and builds data centre modules and sells them to third-party data centre owners. The ASX classifies it in Information Technology, within Software and Services.
Its revenue lines are modular data centres, data centre operations and data centre as a service. In June 2026 it sold a non-core Tasmanian data centre for up to A$520,000, including an A$120,000 earn-out.
Two AI contracts, one lost
DXN announced its maiden AI high-performance computing contract, worth about A$8.8 million for a 1.36MW module, on 3 June 2026. On 24 August 2026 it signed a second, binding A$12.2 million contract with an unnamed AI compute operator for a turnkey 2MW facility.
The second customer's site is targeted to be operational in early calendar 2027. DXN says it is the first phase of a potentially larger deployment, though later phases are not contracted.
The first customer, a US-listed neo-cloud operator, told DXN after quarter end that it intended to cancel following a strategic shift. The company expects a termination payment of about A$4.2 million, or 48 per cent of contract value, including A$1.1 million still to arrive in the December 2026 quarter.
DXN said the customer is unlikely to pursue a larger follow-on campus, which it had earlier described as US$200 million or more and contingent on a proof-of-concept module.
The numbers
For FY26, DXN reported revenue of A$10.1 million, down 33 per cent on the re-presented A$15.1 million of FY25. Gross Profit fell 63 per cent to A$1.8 million, and EBITDA was a loss of A$4.4 million. The results release does not state the currency explicitly.
The September 2026 quarter looked different. Revenue was about A$3.4 million, against A$0.7 million a year earlier, driven by modular data centres at roughly A$2.9 million.
Backlog was about A$30.8 million at 30 September 2026, against A$23.5 million at 30 June, after A$19.3 million of new orders and variations and the removal of the cancelled contract. DXN expects first-half FY27 revenue of about A$11.0 million, including the termination payment.
Cash and capacity
Operating cash flow was an outflow of A$4.7 million in the quarter, which the company attributes mainly to the timing of customer receipts. Cash was A$6.4 million at 30 September, versus A$11.0 million at 30 June, and about A$11.1 million on 28 October.
The higher October figure suggests receipts arrived after the period closed. The company says existing cash supports delivery of its backlog. A A$7.0 million Capital raise in FY26 helps fund extra factory capacity.
DXN operates a 4,200 square metre Welshpool site and is setting up a temporary Seven Hills facility in New South Wales. It signed a Johor, Malaysia Lease in September, with production targeted for the December 2026 quarter, subject to licensing and fit-out. Management expects capacity to rise about sixfold against current Western Australian output once new sites ramp up.
Risks and dates ahead
Customer concentration is the clearest single risk here, as the cancellation showed. Pipeline conversion, factory start-ups and licensing delays could all affect timing, and expansion consumes cash before revenue arrives.
The pipeline stood at 93 projects, of which 28 per cent relate to AI, and 12 were in final negotiations or verbal wins.