Highlights
- DigiCo Infrastructure REIT (ASX:DGT) reported a 71MW long-term SYD1 customer contract in October.
- November AGM materials described 88MW of contracted capacity at SYD1.
- The trust reported FY26 underlying EBITDA of AUD 127 million.
- The AGM presentation detailed a funded 52MW SYD1 expansion programme.
DigiCo Infrastructure REIT (ASX:DGT) owns and develops data-centre infrastructure, with contractual capacity and commissioning schedules central to its business. On 23 November 2026, its quoted security price was AUD 2.375, down 0.21% for the session. Recent disclosures centre on the large SYD1 customer contract.
The developments reported during 2026 involve measurable operating milestones as well as matters that remain subject to subsequent reporting. The relevant distinction is between activities already completed, management guidance and future targets that depend on operational or transaction conditions.
SYD1 Customer Contract and Capacity Expansion
An October announcement described a 15-year contract for 71 megawatts of capacity at the SYD1 data centre, supported by investment-grade Credit support. The November AGM presentation said the remaining 17 megawatts was contracted to colocation customers. That made the disclosed 88-megawatt site capacity fully contracted, although contractual status is distinct from all capacity being built and billing.
The trust reported underlying FY26 EBITDA of AUD 127 million, above its AUD 125 million guidance, and distributions of 12 cents per security. These are company-defined measures and declared payments. The annual results should be read separately from the development programme’s prospective Earnings once additional capacity is operational.
FY26 Performance and Financing Capacity
DigiCo stated that a 20-megawatt improvement programme at SYD1 was completed on time and on budget. The further 52-megawatt capacity expansion is expected to be delivered across FY27 and FY28, and management said the programme was fully funded. This is a forward schedule, not evidence that the expansion is already delivering contracted customer revenue.
The trust’s disclosures also outlined sales of US data-centre Assets and their impact on liquidity. November AGM materials described pro-forma Liquidity of around AUD 1.2 billion and gearing potentially declining from 39% to 18% on the stated sale assumptions. Pro-forma calculations must be distinguished from historical balance-sheet results.
Risks and Uncertainties to Watch
Development risks include electricity access, construction cost, commissioning, customer fit-out and delivery deadlines. The Revenue commencement date can differ from Lease signing. Pro-forma financing measures also depend on settlement of relevant asset sales and the assumptions in management’s presentation.
A signed data-centre contract commits capacity subject to its terms, whereas Operating Revenue depends on delivery, commissioning and billing. The distinction is especially relevant when a substantial part of a development is scheduled for future financial periods. Capacity plans and financing assumptions should not be described as completed assets.
What to Watch Next
The measurable milestones are staged commissioning at SYD1, customer billing commencement, completion of asset disposals and progress on the separate 15MW ADL1 discussions. Future reports can identify how much contracted capacity is actually earning revenue.
Key Insights
The clearest feature of the 2026 disclosures is the scale of contracted Sydney capacity compared with the construction still required. The next published company updates will provide more evidence than assumptions about future performance.